Repair works underway on Coulsons Creek Road

Published

Work to rebuild Coulsons Creek Road in the Upper Hunter, NSW, is now in full swing following more than $48 million in funding provided by the Australian and NSW governments.

The work on Coulsons Creek Road will take place between Merriwa and Willow Tree Road.

The road had been previously completed in 2019, but the vital community connection was significantly damaged by heavy rainfall and subsequent land slips, causing its closure in 2021. 

The upgraded road will feature improved drainage, protection against rock falls, new safety barriers, signage and line marking.

Transport for NSW, Infrastructure NSW and Public Works Advisory worked closely with the Upper Hunter Shire Council on a new design for the road. 

The Australian Government has committed $38.6 million and the NSW Government $9.66 million for the repairs to be carried out.

Daracon Group has been awarded the contract to carry out the work. 

Work is expected to be complete by mid 2025, weather permitting.