Lignum Creek Bridge replacement

Reviewed

Project overview

The NSW Government is providing $6.7 million to replace the Lignum Creek Bridge on the Mid Western Highway, 60 kilometres west of Grenfell to provide a smoother and longer lasting bridge, improve safety and reduce ongoing maintenance costs.

Latest news

Aug 2019 - Work completed

The Lignum Creek bridge replacement project was completed in early May 2019, an impressive eight weeks ahead of schedule.

The NSW Government provided $6.7 million as part of the Bridges for the Bush Program to demolish the existing old wooden bridge and replace it with a new, wider 72 metre long concrete bridge.

The bridge has been replaced for less than $6.2 million which is a half a million dollar cost saving.

Motorists, freight and heavy vehicle operators will have increased efficiency and reliability with the new longer, stronger, wider and safer concrete bridge.

The Lignum Creek Bridge is an important crossing on the Mid Western Highway with more than 144 vehicles travelling on this section of road each day including 45 heavy vehicles which account for 32 per cent of bridge traffic.

The bridge joins Grenfell on the Mid Western Highway with West Wyalong on the Newell Highway.

The project supported local employment and investment by employing 16 people: six people during bridge construction and up to 10 people during road construction.

We thank motorists for their patience during this important project.

Project information

Background

Lignum Creek Bridge, on the Mid Western Highway was built in 1937 and is narrow, in poor condition and nearing the end of its life.

The NSW Government provided $6.7 million for the replacement of the Lignum Creek Bridge as part of the Bridges for the Bush program.

To minimise disruption to motorists on the Mid Western Highway, a side track was built next to the bridge and used to divert traffic during the project construction. The side track has now been removed.

Benefits

  • Longer lasting, smoother and stronger bridge
  • Improved safety for road users
  • Reduced ongoing maintenance costs

 

Project documents

Some documents on this page may not comply with accessibility requirements (WCAG).

If you are having trouble accessing information in these documents, please contact us.

 

Community updates

Contact us

For further information about this project, please contact:

Phone: 1800 167 499

Email:western.projects@transport.nsw.gov.au