Natural Disaster Recovery and slope work - Kings Highway

Reviewed

Project overview

Transport for NSW is carrying out urgent natural disaster recovery work on the Kings Highway at Clyde Mountain. As part of this work, there will be traffic changes on the Kings Highway at Clyde Mountain.

Latest news

Jun 2022 - Tree removal work

The additional tree removal work on the Kings Highway at Clyde Mountain required as a result of ongoing wet weather, is now complete.

May 2022 - Slope remediation work

Natural Disaster Recovery funded slope remediation work on the Kings Highway at Clyde Mountain is now complete.

Project information

Background

Since 2019 there have been multiple Natural Disaster declarations in Eurobodalla Shire for storm, flood and bushfire events. These disasters have highlighted the need for the state road network to be safe and reliable and to ensure that roadside maintenance is adequate.

In early 2021 an arborist report identified approximately 400 high risk trees on the Clyde Mountain Pass section of the Kings Highway. These trees were badly burnt in the 2019/20 bushfires and have become significantly less stable due to the effects of storms and flooding.

Transport for NSW has now removed these trees under full road closure of the Kings Highway at Clyde Mountain. 

Benefits

An extensive program of improvement work will continue on the Kings Highway including safety treatments and slope stabilisation. Where possible, some of this work will be carried out during the full road closure to minimise future impact.

This will improve safety for motorists by removing roadside hazards, improve safety for workers and improve security of the road network by reducing the likelihood of unplanned closures.

We will continue to keep you informed.

Community information

Frequently asked questions (FAQs)

Kings Hwy, Clyde Mt closure, Natural Disaster Recovery work


  • Transport for NSW will remove approximately 400 high risk trees under full road closure of the Kings Highway at Clyde Mountain.

    The closures will be in place from Tuesday 31 August 2021 to early December 2021, weather permitting.


  • During the 2019/20 bushfires, trees along the Kings Highway at Clyde Mountain were badly burnt. These trees have become significantly less stable due to the effects of more recent storms and flooding.

    In early 2021 an arborist report assessed and identified approximately 400 high risk trees that must be removed as they pose a safety risk to road users and workers.

    This work will be funded under Natural Disaster Recovery Funding, ensuring adequate roadside maintenance and a more resilient road network.


  • The Kings Highway will be closed from River Forest Road to Misty Mountain Road.

    Full closures will be in place three days per week from Tuesday to Thursday between 8am and 3pm from Tuesday 31 August until Thursday 16 September.

    The road will open over the September school holidays to allow holiday traffic to travel without impact and work will recommence after the October long weekend.

    From Tuesday 5 October the closures will be in place for an additional hour from 8am to 4pm Tuesday to Thursday until early-December, weather permitting.

    No work will take place on Monday, Friday, weekends, public holidays or school holidays.


  • The closures will be in place Tuesday to Thursday due to lower travel volumes recorded on the Kings Highway on these days. We are keen to carry out this work with as little disruption to motorists, local communities and local businesses as possible, and are aware that business rely on tourist traffic that traditionally travel Mondays, Fridays and weekends. We have purposely planned our work schedule around these peak travel times.

  • We understand the impacts extended closures would have on local communities and business that have already gone through many hardships, and we’ve worked with them on ways to minimise disruption while carrying out this critical safety work

    The revised schedule aims to balance the need to remove the trees as quickly as possible for the safety of road users and minimising extended closures and the impact these might have on the community.

    The revised closure times have been determined in consultation with Eurobodalla Shire Council, Queanbeyan-Palerang Regional Council, emergency services, the freight industry and business groups.


  • To remove the very large damaged trees, arborists will need to cut and drop large sections of the trees to ground level which will block the travel lanes.

    The trees which are up to 25m high will be felled from the up-slopes onto the road which requires both lanes to be closed.

    There is no way to complete the work safely and efficiently without a full closure.


  • Closure times have been determined in consultation with Eurobodalla Shire Council, Queanbeyan-Palerang Regional Council and targeted engagement with stakeholders, including emergency services, the freight industry and business groups. Our goal has been to balance disruption for our transport customers and local communities, including local businesses, with the need to safely and efficiently carry out this urgent natural disaster recovery work


  • Emergency services have been briefed on the road closure impacts. Emergency access will be assessed by the project team in conjunction with emergency services on a case by case basis.

  • We encourage you to plan your journey and travel outside of the road closure times where possible. The road will be open with no impacts on Mondays, Friday and weekends from 3pm to 8am Tuesday to Thursday.

  • The Kings Highway at Clyde Mountain will be closed to all transport customers, including freight. Transport for NSW will continue to keep our stakeholders informed of project progress and any changes to the closure schedule. We encourage all road users to plan your journeys and travel outside of the road closure times where possible.


  • There is no pedestrian access on this section of the Kings Highway at any time. Cyclists, like our other transport customers, will have access to the road outside of the closure times.


  • It takes approximately 15 minutes to reach the hard closure location at Misty Mountain Road from Nelligen and approximately 15 minutes to reach the hard closure location at River Forest Road from Braidwood. To avoid lost time for road users, two soft closure locations will be in place.

    Traffic control will be located at Monkittee Street, Braidwood and at Old Bolaro Road, west of Nelligen from 7.40am to advise motorists they will no longer reach the closure point in time to make it through the hard closure.

    Example (west bound to the tablelands)

    If you are traveling from Nelligen to Braidwood and you reach Nelligen at or later than 7.40am, you will be turned around as you will not make it to Misty Mountain Road in time to get through the closure.

    Example (east bound to the coast)

    If you are traveling from Braidwood to Nelligen and you reach Braidwood at or later than 7.40am, you will be turned around as you will not make it to River Forest Road in time to get through the closure.


  • We explored the possibility of carrying out this work at night, but determined night work presented an unacceptable safety risk to workers. Adequate lighting is needed to complete the work safely and efficiently. In addition, the steep terrain and tree heights do not allow for this work to be completed safely at night.

  • Alternate routes via the state road network will be in place for light and heavy vehicles, with maps available on the project webpage. Motorists are advised to travel outside of closure times or plan their journeys.

    The northern alternate route is via the Hume Highway, Picton Road and the Princes Highway and could add up to 6.5 hours to journeys depending on origin and destination.

    The southern detour is via the Kings Highway, Monaro Highway, Snowy Mountains Highway and the Princes Highway and could add up to 5.5 hours to journeys depending on origin and destination.

    Other local roads are also available as alernate routes.


  • There is a program of maintenance work required for the Kings Highway including slope stabilisation, guardrail and fence replacement, storm water management and asphalt patching.

    Where possible some of this work will be carried out during the full road closure, however further closures may be required for ongoing work.


  • Variable message signs will be in place across the road network advising of the closure. If there are changes to the work methodology or if work stops temporarily we will update Live Traffic and signs.

  • Transport will continue to keep our stakeholders and the community informed throughout the period. If there are changes to the work methodology or work is not carried out, we will update Live Traffic and variable message signs.

    For more information, or to subscribe for email updates, please visit our project website at nswroads.work/clydemountain

    For the latest traffic updates call 132 701, visit livetraffic.com or download the Live Traffic NSW App.

    Follow our Facebook page: NSW Roads

    For more information on the impacts of the Natural Disaster declarations on local roads, please visit the Eurobodalla Shire Council webpage.

    Transport for NSW thanks the community for its patience while this important work is carried out.

Subscribe to stay up to date





 

Privacy Statement: Transport for NSW is committed to protecting your personal information. We will not publish or disclose your personal information to any third parties unless you consent or as authorised by law. Aggregated or depersonalised information which does not identify you, such as summary tables, may be published or disclosed to third parties. Providing personal information is voluntary, however we rely on your participation to ensure the accuracy and reliability of the information obtained and we may not be able to communicate with you directly if you do not provide your personal information.

Your information will be managed by Transport for NSW in accordance with the Privacy and Personal Information Protection Act 1998 and the Health Records and Information Privacy Act 2002. For further information, please see our Privacy Management Plan or contact us at privacy@transport.nsw.gov.au. If you wish to access, correct or remove the personal information collected by us you can email SouthProjects@transport.nsw.gov.au.

 

Project documents

Some documents on this page may not comply with accessibility requirements (WCAG).

If you are having trouble accessing information in these documents, please contact us.

 

Project updates

Detour maps

Media releases

Contact us

For further information about this project, please contact:

Email: SouthProjects@transport.nsw.gov.au

Mail: Kings Highway Clyde Mountain Closure, PO Box 477, Wollongong NSW 2520