Project documents - Northern Beaches Hospital
Project overview
Northern Beaches Hospital project documents
Project documents
Some documents on this page may not comply with accessibility requirements (WCAG).
If you are having trouble accessing information in these documents, please contact us.
Community information
Community agreements
- Community agreement - extended hours in the underpass - January 2020 to end March 2020
Northern Beaches Hospital Connectivity and Network Enhancement Project - Community agreement - underpass night work to end 2019
Northern Beaches Hospital Connectivity and Network Enhancement Project. - Community agreement - Weekend works for Stage 2 Warringah Rd Eastbound till end of March 2019
Northern Beaches Hospital Connectivity and Network Enhancement Project. - Community agreement - Warringah Road eastbound weekend work
Northern Beaches Hospital Connectivity and Network Enhancement Project. - Community agreement - Aquatic Drive and Wakehurst Parkway weekend work
Northern Beaches Hospital Connectivity and Network Enhancement Project. - Community agreement - Weekend works for Stage 2 Eastbound Drainage
Northern Beaches Hospital Connectivity and Network Enhancement Project. - Community agreement - Saturday & Sunday Works Stage 2 May 2018
Northern Beaches Hospital Connectivity and Network Enhancement Project. - Community agreement - Saturday & Sunday Works at Aquatic Drive
Northern Beaches Hospital Connectivity and Network Enhancement Project. - Community agreement - Extended working hours community engagement
Northern Beaches Hospital Connectivity and Network Enhancement Project.
Out of hours work schedule
Forms
- May 2014 feedback form
Northern Beaches Hospital – Connectivity and network enhancements.
Factsheets
- April 2018 factsheet
Vibration fact sheet. - April 2018 factsheet
Extended Working Hours along Frenchs Forest Road, Naree Road and Forest Way - Fact Sheet. - August 2016 factsheet
Flora and fauna.
Community notifications
- December 2018 community update
Northern Beaches Hospital road upgrade project. - October 2018 community update
Northern Beaches Hospital road upgrade project. - May 2018 community update
Northern Beaches Hospital road upgrade project. - December 2017 community update
Northern Beaches Hospital road upgrade project. - November 2016 community update
Northern Beaches Hospital road upgrade project. - April 2016 community update
Northern Beaches Hospital Road Connectivity and Network Enhancement Project. - May 2015 community update
Parking arrangements at Skyline Shops, Frenchs Forest Road East, Frenchs Forest. - May 2015 community update
Environmental Impact Statement – Concept Proposal and Stage1, Submissions Report/Preferred Infrastructure Report. - December 2014 / January 2015 community update
Stage 2 – preferred option for road upgrades along Warringah Road. - October 2014 community update
Northern Beaches Hospital Road Connectivity and Network Enhancement Project. - October 2014 community update
Northern Beaches Hospital connectivity and network enhancement works – have your say. - March 2014 community update
Northern Beaches Hospital – Connectivity and network enhancements.
Project notifications
- August 2020 project update
Completion of the Northern Beaches Hospital road upgrade - March 2020 project update
Opening the Warringah Road underpass to traffic. - December 2019 project update
Northern Beaches Hospital road upgrade project. - August 2019 project update
Northern Beaches Hospital road upgrade project. - August 2017 project update
Northern Beaches Hospital road upgrade project. - January 2016 project update
Northern Beaches Hospital Road Connectivity and Network Enhancement Project. - October 2015 project update
Northern Beaches Hospital Road Connectivity and Network Enhancement Project.
Reports
Compliance reports
- May 2021 Operational noise compliance review report stage 1 and stage 2
Northern Beaches Hospital Road Connectivity and Network Enhancement. - May 2021 Operational traffic compliance report stage 1 and stage 2
Northern Beaches Hospital Road Connectivity and Network Enhancement.
Community consultation reports
- October 2014 community consultation report
Northern Beaches Hospital - Road connectivity and network enhancement project. - July 2014 community consultation report
Northern Beaches Hospital - Road connectivity and network enhancement project.
Options report
- December 2014 options development and selection report
Northern Beaches Hospital - Road connectivity and network enhancement project.
Environment reporting
Biodiversity Offset Package
- April 2020
Biodiversity Offset Package
Ecological monitoring
Operational Water Management
- Approval of Stage 2 Water Management
June 2020. - Stage 2 Water Management Plan
May 2020.
Operational noise
Construction Environment Management Plan
- September 2019 construction environment management plan
Main report - September 2019 construction environment management plan
Appendix B1 - Traffic and access management plan. - August 2016 construction environment management plan
Appendix B2 - Flora and fauna management plan. - August 2016 construction environment management plan
Appendix B3 - Noise and vibration management plan. - September 2019 construction environment management plan
Appendix B4 - Soil and water quality management plan - September 2019 construction environment management plan
Appendix B5 - Heritage management plan. - September 2019 construction environment management plan
Appendix B6 - Air quality management plan. - September 2019 construction environment management plan
Appendix B7 - Waste and energy management plan. - September 2019 construction environment management plan
Appendix B8 - Construction compound and ancillary facilities management plan. - August 2016 construction environment management plan
Appendix B9 - Compliance tracking program. - November 2017 asbestos management plan
Northern Beaches Hospital - Connectivity and Network Enhancement Project. - September 2019 pollution incident response management plan
Northern Beaches Hospital - Connectivity and Network Enhancement Project. - August 2016 community communications strategy
Northern Beaches Hospital - Connectivity and Network Enhancement Project.
Urban and Landscape design report
- June 2016 urban landscape design report
Northern Beaches Hospital Connectivity and Network Enhancement Project.
Water quality reports
- September 2017 to Febuary 2018 surface water analysis
Middle creek catchment. - September 2017 to Febuary 2018 surface water analysis
Curl Curl creek catchment. - September 2017 to Febuary 2018 surface water analysis
Botany Bay catchment. - September 2017 to April 2018 groundwater analysis
- December 2014 water monitoring report
Factual Baseline Water Quality Monitoring Report (24 Months).
Compliance reports
- February 2020 to May 2020
Final six monthly compliance report – Stage 2 - September 2019 to February 2020
Six Monthly Compliance Report – Stage 2 - March 2020 pre-operational compliance report
Stage 2 Pre-Operational Compliance Report - August 2019 pre-operational compliance report
Stage 1 Pre-Operational Compliance Report. - September 2018 to February 2019
Six Monthly Compliance Report. - March 2018 to August 2018
Six Monthly Compliance Report. - September 2017 to February 2018
Six Monthly Compliance Report. - March 2017 to August 2017
Six Monthly Compliance Report. - February 2017
Six Monthly Compliance Report. - December 2015 to June 2016
Six Monthly Compliance Report. - May 2016 compliance report
Pre-construction compliance report
Environmental Impact Stagement - Stage 1
- June 2015 determination
Secretary's environmental assessment report. - June 2015 determination
Instrument of approval. - April 2015 submissions report
Main report with appendix A. - April 2015 submissions report
Appendix B - suggested design changes included with private submission. - April 2015 submissions report
Appendix C - addendum to stage 1 statement of heritage impact. - April 2015 submissions report
Appendix d - updated traffic and transport assessment. - April 2015 submissions report
Appendix e - additional noise and vibration assessment. - October 2014 staged infrastructure application
Concept Proposal and Stage 1 Hospital Connectivity Works. - October 2014 environmental impact statement
Overview. - October 2014 environmental impact statement
Volume 1. - October 2014 environmental impact statement
Volume 2. - October 2014 environmental impact statement
Appendix D - traffic and transport. - October 2014 environmental impact statement
Appendix E - noise and vibration (part 1). - October 2014 environmental impact statement
Appendix E - noise and vibration (part 2). - October 2014 environmental impact statement
Appendix F - biodiversity. - October 2014 environmental impact statement
Appendix G - social and economic impacts. - October 2014 environmental impact statement
Appendix H - draft community consultation framework. - October 2014 environmental impact statement
Appendix I - urban design (part 1). - October 2014 environmental impact statement
Appendix I - urban design (part 2). - October 2014 environmental impact statement
Appendix I - urban design (part 3). - October 2014 environmental impact statement
Appendix I - urban design (part 4). - October 2014 environmental impact statement
Appendix J - aboriginal archaeological survey report. - October 2014 environmental impact statement
Appendix K - non-aboriginal heritage. - October 2014 environmental impact statement
Appendix L - phase 1 contanimation report. - October 2014 environmental impact statement
Appendix M - flooding and hydrology (part 1). - October 2014 environmental impact statement
Appendix M - flooding and hydrology (part 2).
Environmental Impact Stagement - Stage 2
- February 2016 determination
State significant infrastructure assessment. - February 2016 determination
Infrastructure approval. - January 2016 determination
Independent traffic peer review. - January 2016 determination
Independent groundwater peer review. - November 2015 submissions report
Northern Beaches Hospital Road Connectivity and Network Enhancement Project Stage 2. - July 2015 environmental impact statement
Overview. - July 2015 environmental impact statement
Volume 1 (chapters 1 to 7). - July 2015 environmental impact statement
Volume 1 (chapters 8 to 15). - July 2015 environmental impact statement
Volume 1 (chapter 16). - July 2015 environmental impact statement
Appendix C - traffic and transport. - July 2015 environmental impact statement
Appendix D - noise and vibration (part 1). - July 2015 environmental impact statement
Appendix D - noise and vibration (part 2). - July 2015 environmental impact statement
Appendix D - noise and vibration (part 3). - July 2015 environmental impact statement
Appendix D - noise and vibration (part 4). - July 2015 environmental impact statement
Appendix D - noise and vibration (part 5). - July 2015 environmental impact statement
Appendix E - biodiversity. - July 2015 environmental impact statement
Appendix F Part 2 - socio-economic impacts. - July 2015 environmental impact statement
Appendix F Part 2 - draft community consultation framework - July 2015 environmental impact statement
Appendix G - urban design and visual impact assessment - July 2015 environmental impact statement
Appendix H - aboriginal heritage - July 2015 environmental impact statement
Appendix I - non-aboriginal heritage. - July 2015 environmental impact statement
Appendix J - air quality. - July 2015 environmental impact statement
Appendix K - contamination. - July 2015 environmental impact statement
Appendix L - surface water (part 1). - July 2015 environmental impact statement
Appendix L - surface water (part 2). - July 2015 environmental impact statement
Appendix M - groundwater (part 1). - July 2015 environmental impact statement
Appendix M - groundwater (part 2). - July 2014 staged infrastructure application report
Stage 2 Network Enhancement Works.