News archive - Coffs Harbour Regional Boat Ramp

News archive for the Coffs Harbour Regional Boat Ramp.

Jan 2024 – Sand Pump Trial update

In April 2023, four jet pumps were installed as part of Transport’s Coffs Harbour Sand Management Plan.

These pumps are regularly in operation, typically on a monthly basis. However, they have been operating more frequently to address the increased sand accumulation caused by recent weather.
 
The rock wall (groyne) is being built to the west of the boat ramp channel. This groyne will direct sand towards the existing jet pumps and prevent sand from entering the inner boat ramp area.
 
Mobile plant, trucks and machinery will be on site, and the boat ramp and channel will remain open.

Installation of the groyne is expected to be completed prior to the long weekend, weather and maritime conditions permitting.

The construction of the groyne is part of the scope and budget of the sand management trial.  The trial is expected to operate until mid-2025 and will help to inform a long-term strategy.

Nov 2023 – Project progress

Jordan Esplanade eastern works are now complete, and the shared path is now in place connecting the boat ramp to the southern breakwall. Additional sections of path will open in the coming weeks around the southern side of the carpark, and most of the landscaping and planting in these areas is also complete.

The main boat ramp carpark is closed however, it will not impact use of the boat ramp, which will remain accessible throughout this time. Access may change from time to time to accommodate the works and we will provide updates via this website and stakeholder communications.

Works have also commenced in the amenities block area with the installation of the rising sewer main, and installation of electrical services for new lighting throughout the western end of the project.   

Overflow and alternate trailer parking has been established and will remain open throughout the construction of the boat ramp carpark (click here to view map (PDF, 354.48 KB)). 

The cleaning table has been relocated and reinstalled adjacent to the boat ramp and is fully operational. Please keep this clean and use the bins provided for waste. The cleaning table will continue to be maintained by Coffs Harbour City Council.

Recent weather conditions caused an unexpected and sudden build-up of sand in the channel in late October, which was causing navigation difficulties during low tide. The situation is now resolved (see latest Hydrographic Survey on this page below.

See our Sand Management page for more details.
 

Sept 2023 - Reopening of Jordan Esplanade, Stage 2 works and closure of the main car park

Jordan Esplanade eastern works are almost complete and the footpath now in place connecting the boat ramp to the southern breakwall. 

From Wednesday 4 October, Jordan Esplanade will be re-opened, and the main boat ramp carpark will be closed for the Stage 2 upgrade. This will not impact use of the boat ramp, which will remain accessible throughout this time. 

Overflow trailer parking has been established and will remain open throughout construction. We have allowed for vehicular and trailer access to the boat ramp during the car park work (see map for details). We expect the car park work to be finished and reopened in December 2023, weather permitting.

Corflute signs are visible in various locations to direct boaters to the overflow parking including pedestrian access.

The larger cleaning table will be temporarily relocated and reinstalled adjacent to the boat ramp. Aside from relocation during the boat ramp works, the cleaning tables are normally (and will continue to be) maintained by Coffs Harbour City Council. 

Stage 2 works include:

  • extending the existing main carpark to include additional parking for cars, boats and trailers
  • new carpark entrance at the western end of the carpark
  • blocking the entry adjacent to the boat ramp off Jordan Esplanade (for safety reasons)
  • diverting traffic along Jordan Esplanade road opposite the main carpark
  • new road signage
  • new rigging and de-rigging bays around the main carpark
  • a new shared pathway (2.5m) for walking/cycling
  • new amenities facility
  • new Lighting and signage
  • recreational furniture including seating and tables
  • pedestrian pathway on south side of Jordan Esplanade with access to Gallows beach carpark and to amenities facility in the main carpark area
  • landscaping
  • extending services, including water, power and sewerage.

Aug 2023 - Upcoming changes to parking and cleaning tables

Work onsite is continuing at a steady pace, as the final adjustments are made to Jordan Esplanade and the footpaths are completed. We will soon be ready to reopen the road and start work on the main car park. Please see our 4 week look-ahead (PDF, 485.19 KB) to see the work that will be happening in September and keep an eye on this site for exact dates.

The Boat Ramp webcam has been upgraded to the latest technology and reinstalled. You can view its live feed here.

In a few weeks, the cleaning tables will be closed due to our work in the area and the larger table will be temporarily relocated and reinstalled. Aside from their relocation during the boat ramp works, these tables are normally (and will continue to be) maintained by Coffs Harbour City Council.

Jan 2023 – Stage 2 work begins and latest map

Work on Stage 2 of the Boat Ramp began on 16 January 2023. The diagram below indicates changes you will be seeing over the next four weeks.

Note that the Western Gallows Beach car par entrance will be temporarily closed for drainage work between 18 January and 18 February. Another site compound (for stage 2) will be established in the green area on the diagram above.

Please take extra care when in the area, noting that the boat ramp itself will remain open throughout construction.

The boat ramp channel is currently clear, with an average depth of between 1.5m & 2.5m across the channel. As such, TfNSW has stood down the Cutter Suction Dredge, which will remain moored in the harbour until it is needed again. This means that it will not be operating in the week of 22 January as previously planned, but the channel will be monitored daily and if required, the dredge can recommence operations to ensure the channel is kept clear. The Cutter Suction Dredge will recommence operations from 30 January.

The most recent hydrographic map is below.

Dec 2022 – Sand Management

As part of the Transport NSW plan to manage the sand build-up in the channel, dredging has continued at the Boat Ramp. Over the next few weeks, we will dredge using an excavator on a barge in the water. 
Half the boat ramp will close on 22 December to allow the barge and excavator to be floated and will remain open during dredging.
Dredging operations will take place over the next four weeks as scheduled below:

  • 22 December - 24 December
  • 27 December - 30 December
  • 2 January - 6 January 2023

Half the boat ramp will close on 6 January to allow the barge and excavator to be demobilised and open immediately after. 

From 9 January our current cutter suction dredge will return to maintain dredging throughout the new year.
These actions will allow us to ensure the boat ramp remains accessible throughout the peak holiday period.


Trial of a sand-pumping system

In November Transport for NSW started planning for trial of a sand-pumping system. The trial is targeting an installation and commissioning date for all specialist equipment as early as March 2023.

This will see sand pumped out of the channel by a series of pumps and pipelines to the sand storage area nearby. It is a trial system to assess its effectiveness, so results will depend on how the trial goes, but if successful, it could see an automatic removal of sand on a permanent basis. 

Stage 2 work

Stage 2 work on the boat ramp (the car park, amenities, and road works) will begin on 16 January 2023. From 5 February onward sections of the carpark may be closed to facilitate equipment storage and a site compound.

In preparation for construction the fish cleaning tables and washdown areas will be temporarily relocated. 

We anticipate the main car park will close in mid-2023. We are currently assessing options for alternate parking sites and will share information as soon as it’s available.
 

Nov 2022 – Sand Management Plan

Transport for NSW has been working hard to find options for the sand build-up at the Boat Ramp. Today we release our Sand Management Plan which details our strategy for managing this sand build-up. You can find the plan under “Reports” in the Documents section below.

We will continue to provide regular hydrographic maps of the boat ramp channel and harbour showing depths in the area. In addition to this, the live webcam vision at the Coffs Harbour Boat Ramp is on site and continues to provide members of the community a live feed of the coastal conditions, to help boaters and skippers prepare for a safe trip.

If you do have any specific questions about the Coffs Harbour Boat Ramp or Sand Management or you can call (1300 778 928) or email us at coffsboatramp@transport.nsw.gov.au and we will respond as soon as possible.

Nov 2022 – Dredging resumes today

The cutter suction dredge has started dredging today to maintain channel depth at the boat harbour and will continue to clear the channel.

We have Boating Safety Officers on site providing advice to boaters using the boat ramp to ensure the safety of all waterway users.

Be mindful of where the cutter suction vessel is and ensure you stay well clear when it is operating.

We recommend that skippers do not attempt to access the channel and boat ramp at low tide due to sand build up.

Boaters are reminded of their responsibility to assess conditions before negotiating any marine channel.

 

Nov 2022 – Cutter Section Dredging to recommence

As part of the Transport NSW plan to manage the sand build-up in the channel, cutter suction dredging will recommence from Friday 11 November 2022. This activity is scheduled for four weeks, so will conclude around 9 December. Please take care in the area and look out for the dredging barge on the water.

Oct 2022 – Hydrographic Survey

This is the latest hydrographic map of the boat ramp channel and harbour showing depths in the area.

Note that this survey was taken on 27 October 2022. Note that seabed conditions could change rapidly due to waves and currents. Extreme caution should be used when navigating the boat ramp entrance area.

You can download our latest hydrographic surveys in Project Documents on this page or by clicking on this latest news image.

Sep 2022 – Extra dredging

Transport for NSW has secured a cutter-suction dredge which will increase the amount of sand we are able to dredge from the boat harbour channel.

We will close half of the boat ramp on 22 September to allow for the dredge barge to be assembled. Cutter-suction dredging will start after this and continue until Friday 30 September. The boat ramp will remain open throughout the works, however we will close half the boat ramp on Saturday 1 October to allow the barge to be disassembled.

During cutter-suction dredging land-based dredging will stop with further dredging planned later in October.

Please take extra care in the area during this period.

Sep 2022 – Project status

Stage One of the Coffs Harbour boat ramp project is now complete. This stage has delivered an additional two lanes to the boat ramp and two new pontoons.

Transport for NSW remains committed to keeping the boat ramp open. Dredging by a land-based excavator is continuing, while a cutter suction dredge has been sourced and is due to commence work in September.

We have engaged a consultant to provide options to manage sand migration at the boat ramp in the long term. This may include further structural work to the newly-extended breakwater or additional structures. When decided, the community will be informed of the plans via a Review of Environmental Factors.

We have also sourced funding to commence a sand transfer system trial at the boat ramp. We are currently in negotiation with a supplier to provide a concept design for this system. This system will use fixed jet pumps to dredge sand from the area.

Stage Two of the upgrade work is due to commence shortly. We are currently finalising details with the preferred contractor. This work includes a realignment of Jordan Esplanade to provide extra spaces in the car park, a new amenities block and new rigging and derigging bays.