2017 photos - part 1 - Photo galleries - Grafton Bridge additional crossing of the Clarence
Project overview
The NSW Government is funding this $240 million project which involves building an additional 525 metre bridge 70 metres downstream from the existing road and rail bridge. The project also includes upgrading parts of the road network in Grafton and South Grafton to connect the new bridge to the existing road network. The new bridge will consist of two lanes but has been designed to be increased to four lanes when traffic levels require it.












The Maeve Anne arrives at the mouth of the Clarence River, Yamba (April 2017)
Aerial view of the temporary jetty being built (May 2017)
Crane pad earthworks on the northside (May 2017)
Construction of the new car park on Pound Street, Grafton (May 2017)
Earthworks for the bridge approach in South Grafton (May 2017)
Monitoring of soft soil work (May 2017)
Aerial view of the crane and existing bridge, looking north (June 2017)
Crane and piling rig on the northside (June 2017)
The Maeve Anne being moved into place by a tug (June 2017)
View of work on the southside (June 2017)
Work on the southside with the existing bridge in the background (June 2017)
Preparing for the first concrete pour for the new bridge piles (July 2017)