2017 photos - part 2 - Photo galleries - Grafton Bridge additional crossing of the Clarence
Project overview
The NSW Government is funding this $240 million project which involves building an additional 525 metre bridge 70 metres downstream from the existing road and rail bridge. The project also includes upgrading parts of the road network in Grafton and South Grafton to connect the new bridge to the existing road network. The new bridge will consist of two lanes but has been designed to be increased to four lanes when traffic levels require it.












Soft soil work south of the Clarence River (July 2017)
Regular water monitoring on the Grafton bridge project (July 2017)
The Grafton bridge project team at the NAIDOC Week Family Fun Day (July 2017)
Residents at 1932 Grafton Bridge opening join in the 85th birthday celebration (July 2017)
Pouring concrete for the first marine pile (August 2017)
Preparing to pour concrete for a land pile on the south side of the Clarence River (August 2017)
Marine pile skirt relocated to river bank in preparation for lifting onto marine piers (Sept 2017)
Marine piling in the Clarence River (September 2017)
Sheet piling for the new pump station in Grafton (September 2017)
Twilight photo looking north from the southern embankment (September 2017)
The Rhumb barge arrives to work on the project (October 2017)
Grafton resident John Perrett speaks with a project team member during an information session (October 2017)