Arncliffe Station Platform Canopy Extension

Reviewed

Project overview

The program is designed to simplify and modernise the rail network. Passengers will be able to access more services on a simpler and more reliable network through the delivery of better infrastructure, new trains and extra services.

Project scope

  • extended the canopy to cover almost the entire length of platforms 3 and 4. This has increased weather protection and helped customers use the whole platform, reducing crowding at busy times
  • installed more CCTV and lighting to improve safety
  • provided more seats along the platform
  • provided more digital information boards and a PA system to keep customers informed.

Customer benefits

  • a 30 per cent increase in peak services on the T4 Eastern Suburbs & Illawarra Line
  • extra services from Cronulla, Waterfall and Hurstville
  • space for 6,000 more customers on the T4 Line during the peak hour.

Project status

Work to extend the platform canopy on platforms 3 and 4 is now complete.

 

Planning
In progress
Complete

Register for updates

To find out more and register for updates, visit the More Trains, More Services Construction Map.

Go to map

 

 

Contact us

Email: projects@transport.nsw.gov.au 
 
Project Infoline: 1800 684 490
 
24/7 Construction Response Line: 1800 775 465