The Escort Way and Henry Parkes Way safety upgrade - Saving Lives on Country Roads
Project overview
The NSW Government is funding $12 million for safety upgrades along the 96 kilometre section of road between Orange and Parkes over the next two years.

Project information
Background
Cabonne Council and Parkes Shire Council, on behalf of Transport for NSW, are delivering safety improvements on The Escort Way and Henry Parkes Way between Orange and Parkes.
The safety upgrades will be delivered along the 96-kilometre section of road over the next two years, with the objective to reduce occurrence and severity of run off road and head on crashes.
Read more about the benefits of safety treatments on Towards Zero Saving lives on country roads.
The 8 projects include clear zone improvements, installing and replacing safety barrier and 8 intersection upgrades.
The intersections to be upgraded are Mousehole Lane, Peabody Road, Rosamel Lane, Healeys Road, Lake Endeavour Road, Cooka Hills Road, Bindogundra Road, Hunts Crossing Road, Massurit Lane and Kamandra Lane.
The safety upgrades have been split into two stages.
Stage one
- Monument project, 32 kilometres west of Orange, delivered by Cabonne Council
- Red Hill project, two kilometres west of Manildra, delivered by Cabonne Council
- Cabonne Boundary project, 14 kilometres west of Manildra, delivered by Cabonne Council
- Fairview project, 32 kilometres west of Manildra, delivered by Parkes Shire Council
- Bumberry Hills project, 19 kilometres west of Manildra, delivered by Parkes Shire Council.
Stage one works will be completed by Dec 2022
Stage two
- Lake Endeavour Road project, 25 kilometres west of Manildra, delivered by Parkes Shire Council
- Cooka Hills Road project, 36 kilometres west of Manildra, delivered by Parkes Shire Council
- Massurit Lane project, 41 kilometres west of Manildra, delivered by Parkes Shire Council
Planning is underway for Stage 2 works.
Key features
Key features of the 8 projects:
Monument
- Vegetation clearing, safety barrier installation
Red Hill
- Intersection upgrade at Rosamel Lane, shoulder widening, vegetation clearing and safety barrier installation
Cabonne Boundary
- Shoulder widening, vegetation clearing and safety barrier installation
Fairview
- Shoulder widening, vegetation clearing and safety barrier installation
Bumberry Hills
- Shoulder widening, vegetation clearing and safety barrier installation
Lake Endeavor
- Shoulder widening, vegetation clearing, safety barrier installation and intersection upgrade at Lake Endeavour Road
Cooka Hills Road
- Shoulder widening, vegetation clearing, safety barrier installation and intersection upgrades at Cooka Hills Road and Bindogundra Road
Massurit Lane
- Shoulder widening, vegetation clearing. safety barrier installation and intersection upgrades at Kamandra Lane, Hunts Crossing Road and Massurit Lane
Project documents
Some documents on this page may not comply with accessibility requirements (WCAG).
If you are having trouble accessing information in these documents, please contact us.
Project notifications
- September 2021 project notification
Work continues on The Escort Way and Henry Parkes Way between Orange and Parkes.
- April 2021 project notification
Work starts on The Escort Way and Henry Parkes Way between Orange and Parkes from Monday 3 May.
Media releases
- Safer journeys between Orange And Parkes
10 May 2021