Mona Vale Road East - Mona Vale Road upgrade
Project overview
The Mona Vale Road East upgrade includes 3.2 kilometres of Mona Vale Road between Manor Road, Ingleside, and Foley Street, Mona Vale. The upgrade will improve safety with additional lanes, widened shoulders, a separated median and a heavy vehicle arrester bed.

Latest news
Mar 2022 - Construction update
Construction has progressed along the corridor and motorists would have noticed the two traffic switches carried out over the last few months. Traffic is now travelling on the new road pavement allowing us to continue work on the retaining walls, which once complete will form part of the new westbound lanes. You can find more information in the Construction Update (PDF, 1.37Mb)
Project information
About the project
The NSW Government is upgrading Mona Vale Road from two lanes to four lanes between Terrey Hills and Mona Vale. The project will be staged to provide customers with a better travelling experience and to improve safety and traffic efficiency.
Mona Vale Road East experiences congestion as a result of the steep grade and limited safe vehicle overtaking opportunities which increases travel times. The proposed road upgrade for Mona Vale Road East would provide:
- Additional lanes for climbing and descending to improve travel time in both directions
- Widened shoulders and median separation to improve safety
- 80km/h speed limit between Mona Vale and Belrose once the road upgrades for both Mona Vale Road East and Mona Vale Road West are completed
- Facilities for cyclists and pedestrians
- Bus priority measures.
What is happening now?
The NSW Government is investing $140 million to upgrade Mona Vale Road between Manor Road, Ingleside, and Foley Street, Mona Vale, from two to four lanes to improve safety and traffic efficiency.
Transport for NSW has awarded the contract for construction to Georgiou Group Pty Ltd. The construction started in January 2019 and is expected to complete in 2022, weather permitting.
Over the last several months we have been carrying out clearing activities such as removing vegetation in the project area. We have also been removing large amounts of unexpected asbestos contaminated soils from the project area.
Coming up activities include survey and investigation work to locate underground utilities between Mona Vale Cemetery and Foley Street including Ponderosa Parade and Samuel Street. We will also clear some vegetation in the area to enable the future road widening.
Some of the excess soil and rock from the Mona Vale Road East construction site will be reused at the Mona Wale Road West site to build an embankment in readiness for the future widening work on the Mona Vale Road West project. We have completed vegetation clearing in the section north of Mona Vale Road between Kimbriki Road and Tumburra Street, Ingleside as part of the Mona Vale Road West early work and preparing the site to receive fill material from the main work in the east.
The project team will continue to engage extensively with the community to minimise the impact wherever possible.
Key features
The key features of the Mona Vale Road East upgrade include:
- Widening Mona Vale Road between Manor Road, Ingleside and Foley Street, Mona Vale from two lanes to four lanes with a central concrete safety barrier. The concrete safety barrier would be located from east of Manor Road to west of Daydream Street
- Providing three metre wide shoulders along Mona Vale Road between Manor Road and Daydream Street to allow a safer area for breakdowns and on-road cyclists
- Replacing the existing roundabout on Mona Vale Road at the intersection of Ponderosa Parade and Samuel Street with new traffic lights and signalised pedestrian crossings on all legs
- Providing new bus priority lanes on Mona Vale Road on the approaches to and departures from the intersection of Ponderosa Parade and Samuel Street
- Relocating the eastbound bus stop on Mona Vale Road near the Ponderosa Parade and Samuel Street intersection further east to the departure side of the intersection
- Providing a three metre wide shared path along the northern side of Mona Vale Road for pedestrians and cyclists. This is currently being redesigned.
- Providing a three metre wide shared path along the southern side of Mona Vale Road between Ponderosa Parade and Foley Street for pedestrians and cyclists
- Changing the speed limit from 70km/h to 80 km/h once the road upgrade work is complete
- Implementing a 40km/h truck and bus speed limit for the downhill descent from Ingleside Road to the base of the escarpment
- Providing a truck arrester bed, for eastbound vehicles next to Walana Crescent
- Building six fill retaining walls up to six metres in height and five cuttings up to 16 metres in height along the length of Mona Vale Road due to the local terrain
- Providing fauna connectivity measures
- Upgrading the existing road and cross drainage systems including the construction, reconstruction and extension of the road drainage network
- Establishing temporary site compounds and stockpile locations during construction
- Landscaping over the length of the proposal
- Installing traffic monitoring cameras at all signalised intersections to assist with traffic management.
Project documents

Artists impression
Contact us
For further information about this project, please contact:
Phone: 1800 633 332
Email: monavaleroad@transport.nsw.gov.au
Mail: Mona Vale Road Upgrade, PO Box 973 Parramatta NSW 2124