Latest News
August 2025 – Upcoming day and night works
Work on site will continue in September. Night work, at times, will be carried out between 7pm and 6am, Mondays to Thursdays, from Monday 1 September to Tuesday 30 September 2025.
For more information about work and traffic changes during September view the September resident update (PDF, 282.54 KB).
August 2025 – Upcoming full road closure
A single night closure of the M1 Princes Motorway (Mount Ousley Road) and Picton Road will occur on Sunday 24 August between 8pm to 4am.
For more information on the closure view the M1 Princes Motorway single night closure notification (PDF, 283.54 KB).
July 2025 - Project update
The project has made good progress so far this year with some major milestones achieved. View the July 2025 project update (PDF, 3.02 MB) to find out more about what the project team has been doing on and off site, and what’s coming up.
July 2025 - Upcoming day and night works
Work on site will continue in August. Night work, at times, will be carried out between 7pm and 6am, Mondays to Thursdays, from Monday 4 August to Thursday 28 August 2025.
For more information about work and traffic changes during August view the August resident update (PDF, 279.08 KB).
July 2025 – Mount Ousley Road shared path bridge go ahead and community consultation summary report
The Mount Ousley Road shared path bridge has received the go ahead and will now move into the detailed design stage.
The shared path and bridge will now be delivered as part of the Mount Ousley interchange project.
During the community consultation period in April and early May 2025, Transport received 233 pieces of feedback. There was strong support for the improved access to key destinations that the bridge will provide for those walking and cycling.
Thank you to everyone who provided feedback.
A community consultation summary report (PDF, 11.8 MB) outlining what we heard is now available.
July 2025 – Project overview animation 2025
Watch the latest project overview animation for the Mount Ousley interchange project.
July 2025 – Drop-in information session
Would you like to learn more about the Mount Ousley interchange project? Come and meet the project team at Mount Ousley Public School on Thursday 31 July 2025 to ask your questions and learn more about how the project is progressing.
Come and drop in at any time between 2.30pm and 6pm.
June 2025 – Upcoming day and night works
Work on site will continue in July. Night work, at times, will be carried out between 7pm and 6am, Mondays to Thursdays, from Tuesday 1 July to Thursday 31 July 2025.
For more information about work and traffic changes during July view the July resident update (PDF, 278.01 KB).
June 2025 - Rescheduled full road closures in June
Rescheduled road closures of the M1 Princes Motorway (Mount Ousley Road) and Picton Road will occur on Sunday 22 June, Monday 23 June and Wednesday 25 June between 8pm and 4am.
For more information on the closures view the M1 Princes Motorway rescheduled road closures notification (PDF, 245.96 KB).
May 2025 – Upcoming day and night works
Work on site will continue in June. Night work, at times, will be carried out between 7pm and 6am, Mondays to Thursdays, from Sunday 1 June to Monday 30 June 2025.
For more information about work and traffic changes during June view the June resident update (PDF, 212.62 KB) (PDF, 212.62 KB).
May 2025 – Changes to upcoming full road closures
Due to recent wet weather, there will be changes to the upcoming planned multiple night closures of the M1 Princes Motorway (Mount Ousley Road) from Bulli Pass to Memorial Drive and Picton Road between M1 Princes Motorway and Almond Street at Wilton.
Full road closures planned for Sunday 25 May and Wednesday 28 May have been postponed.
A full road closure to carry out emergency pavement repair and road barrier modification work will occur on Monday 26 May between 8pm and 4am.
May 2025 – Full road closures in May and June
Closures of the M1 Princes Motorway (Mount Ousley Road) and Picton Road are planned to occur in May and June 2025, starting from Sunday 25 May between 8pm and 4am.
For more information on the closures view the M1 Princes Motorway multiple night closures notification (PDF, 269.25 KB).
April 2025 – Upcoming day and night works
Work on site will continue in May. Night work, at times, will be carried out between 7pm and 6am, Mondays to Thursdays, from Thursday 1 May to Thursday 29 May 2025.
For more information about work and traffic changes during May view the May resident update (PDF, 270.65 KB).
March 2025 – Upcoming day and night works
Work on site will continue in April. Night work, at times, will be carried out between 7pm and 6am, Mondays to Thursdays, from Tuesday 1 April to Wednesday 30 April 2025.
For more information about work and traffic changes during April view the April resident update (PDF, 268.16 KB).
March 2025 – Upcoming vegetation removal
As part of the project, extensive vegetation removal, including mulching, will commence on the southern side of the M1 Princes Motorway near the University of Wollongong in late-March and is expected to continue into May, weather permitting.
For more information on the upcoming vegetation removal work view the vegetation removal notification (PDF, 267.1 KB).
February 2025 - Upcoming day and night works
Work on site will continue in March. Night work, at times, will be carried out between 7pm and 6am, Mondays to Thursdays, from Monday 3 March to Monday 31 March 2025.
For more information about work and traffic changes during March view the March resident update (PDF, 270.3 KB).
January 2025 – Project update
To learn more about what‘s been happening on the project over the last 12 months and what’s coming up view the January 2025 project update (PDF, 1.34 MB).
January 2025 – Upcoming day and night works
Work on site will continue in February. Night work will be carried out as required between 7pm and 6am, Mondays to Thursdays, from Monday 3 February to Thursday 27 February 2025.
For more information about work and traffic changes during February view the February resident update (PDF, 265.42 KB).
January 2025 - Upcoming day and night works
We hope everyone had a safe and happy holiday season. Work on site will recommence in January 2025. Night work will be carried out as required between 7pm and 6am, Mondays to Thursdays, from Wednesday 8 January to Thursday 30 January 2025.
For more information about work and traffic changes during January view the January resident update (PDF, 280.79 KB).
November 2024 – Upcoming full road closure
The closure of the M1 Princes Motorway (Mount Ousley Road) from Bulli Pass to Memorial Drive and Picton Road between M1 Princes Motorway and Almond Street at Wilton on Wednesday 13 November was disrupted by weather and critical activities were unable to be completed.
To carry out these activities, a full night closure will occur on Sunday 8 December, between 8pm to 4am, weather permitting.
For more information on the impacts during the closure view the upcoming closure of the M1 Princes Motorway notification (PDF, 327.97 KB).
November 2024 – Upcoming day and night works
Work on site will continue in November and December. Night work will be carried out as required between 7pm and 6am, Mondays to Thursdays, from Monday 18 November to Thursday 19 December 2024.
For more information about work and traffic changes during November and December view the latest resident update (PDF, 329.58 KB).
The project site will be closed over the upcoming holiday period from Friday 20 December 2024 until Monday 6 January 2025.
November 2024 - Temporary pedestrian and cyclist changes
The pedestrian bridge over the M1 Princes Motorway at Northfields Avenue is being extended to improve access for pedestrians and cyclists. From Monday 18 November to Thursday 19 December the bridge will be closed and a temporary detour for pedestrians and cyclists will be in place.
To learn more view the November notification (PDF, 249.79 KB).
October 2024 – Construction update
Work on site will increase significantly in October and November. Night work will be carried out as required between 7pm and 6am, Mondays to Thursdays, from Monday 21 October until Friday 15 November 2024.
For more information about work and traffic changes during October and November view the latest resident update (PDF, 301.9 KB).
October 2024 - Full road closures in November
Closures of the M1 Princes Motorway (Mount Ousley Road) from Bulli Pass to Memorial Drive and Picton Road between M1 Princes Motorway and Almond Street at Wilton are planned to occur during November, starting on Sunday 3 November between 8pm and 4am.
For more information on the closures view the M1 multiple night closures notification (PDF, 235.26 KB).
September 2024 – Drop-in information session
Would you like to learn more about the Mount Ousley interchange project?
Come and meet the project team at Mount Ousley Public School on Thursday 26 September 2024 to ask your questions and learn more about the plans for the project and how it will be built.
Come and drop in at any time between 2.30pm and 7pm, view the community invite (PDF, 206.22 KB).
July 2024 – Upcoming night work in August
In addition to day work, night work will be carried out as required between 7pm and 6am, Mondays to Thursdays, from Monday 5 August until Thursday 29 August 2024.
For more information view the August resident update (PDF, 225.49 KB).
June 2024 – Night and weekend work in July
In addition to day work, night work will be carried out as required between 7pm and 6am, Mondays to Thursdays, from Monday 1 July until Thursday 1 August 2024. Work will also be carried out on Irvine Street Saturday 6 July and Saturday 13 July between 8am and 6pm and Sunday 14 July 8am and 2pm.
For more information view the July resident update (PDF, 213.51 KB).
May 2024 – Project update
The Urban Design and Landscape Strategy Report was on display in May and June 2024. To learn more view the project update (PDF, 4.59 MB).
May 2024 - Night work in June
In addition to day work, night work will be carried out as required between 7pm and 6am, Mondays to Thursdays, from Monday 3 June until Thursday 27 June 2024.
For more information view the June resident update (PDF, 270.13 KB).
April 2024 – Night work in April and May
In addition to day work, night work will be carried out as required between 7pm and 6am, Mondays to Thursdays, from Monday 22 April until Thursday 30 May 2024.
For more information view the April and May resident update (PDF, 2.25 MB).
March 2024 – Project update
Early work activities are underway on the project. To learn more about what’s happening now and key changes from the concept design view the project update (PDF, 2.27 MB).
March 2024 – Night work in March and April
Night work may be carried out Monday to Thursday between 6pm and 7am, from Monday 25 March until Thursday 18 April 2024.
For more information view the March and April resident update (PDF, 794.83 KB).
February 2024 – Project update
Detailed design is progressing and early work will start in the coming weeks.
Major work is planned to start in late 2024 with the project expected to take about four years to complete, weather permitting.
For more information view the February project update (PDF, 494.15 KB).
January 2024 – Contract awarded to design and build the interchange
The contract to design and build the $390 million Mount Ousley interchange, has been awarded to Fulton Hogan.
Early work will start in the coming months, including survey and geotechnical investigations, utility relocation and vegetation clearing.
In the coming weeks the community will be updated on the next stages of the project.
Contact us
For further information about this project, please contact:
Phone: 1800 792 918
Email: MountOusleyInterchange@fultonhogan.com.au
Mail: Mount Ousley interchange, PO Box 477 Wollongong NSW 2520