Spring Creek Bridge replacement
Project overview
The Australian and NSW Governments have committed $13.1 million to replace Spring Creek Bridge over Spring Creek on the Kamilaroi Highway, west of Narrabri.

Latest news
July 2025 – Progress continues at Spring Creek Bridge on the Kamilaroi Highway
The last of the 48 pre-cast concrete girders have been installed as construction of the new Spring Creek Bridge on the Kamilaroi Highway, west of Narrabri, continues to take shape.
The next major step as part of the new Spring Creek Bridge replacement project will involve pouring the bridge deck.
The bridge is on track for completion in late 2025.
September 2024 – Construction on the new Spring Creek Bridge to start
Construction on the new Spring Creek Bridge on the Kamilaroi Highway in north-western NSW is set to start with residents, tourists and freight operators set to benefit from a wider, stronger bridge.
For more information, read the latest media release.
August 2024 - Contract awarded and work set to start
For more information read the August project update (PDF, 915.5 KB).
July 2024 – Changed traffic conditions on the Kamilaroi Highway at Spring Creek
Traffic is scheduled to be switched on to the side track on Monday 22 July 2024 in preparation for the bridge replacement project later this year. To find our more, please read the notification letter (PDF, 406.23 KB).
July 2024 - On your marks: tools at the ready to build the new Spring Creek Bridge
Work to build the new Spring Creek Bridge on the Kamilaroi Highway near Narrabri is expected to start in September 2024.
Following a competitive tender process, Saunders Civilbuild Pty Ltd has been confirmed as the successful contractor to build the new 64-metre-long bridge. For more information, read the full media release.
Project information
Background
Spring Creek Bridge is a major crossing over Spring Creek on the Kamilaroi Highway, located 9.5 kilometres west of Narrabri.
The bridge is an important link for road users travelling on the Kamilaroi Highway between Narrabri and Wee Waa, as well as for the local community and agricultural industry.
The existing bridge is an eight-cell cast in-situ reinforced concrete box culvert structure which was built in 1968.
Spring Creek Bridge has previously been subject to heavy vehicle restrictions and detours while essential safety works were carried out to reinforce the bridge structure.
This project will see the existing bridge replaced with a new, wider bridge that meets modern design standards, and current and future road network requirements.
Its replacement will be a stronger, longer lasting structure which will improve access for wide loads and improve safety for all vehicles.
A Review of Environment Factors (REF) (PDF, 52.34 MB) was determined in May 2023 and can be viewed in the document links on this page.
Benefits
Project benefits include:
- improved safety for road users
- stronger, longer lasting bridge
- improved access for freight by providing a wider bridge
- reduced ongoing maintenance costs.
Completed works
Following a competitive tender process, Saunders Civilbuild Pty Ltd was confirmed as the successful contractor to build the new 64-metre-long bridge over Spring Creek on the Kamilaroi Highway.
Construction officially commenced on 16 September 2024.
Completed works include:
- Establishment of a temporary sealed side track in July 2024 to facilitate two-way traffic flow on the Kamilaroi Highway during construction of the new bridge
- site establishment in September 2024
- demolition of the old bridge structure from October to November 2024
- piling
- substructure works
- girder placement.
Next steps
- Now that girder installation is complete, crews have begun work to construct the new bridge deck.
- It is expected that the new bridge will be open to traffic by late 2025, weather permitting.
Project documents
Project notifications
- July 2025 notification (PDF, 2.55 MB)
Spring Creek Bridge replacement - August 2024 notification (PDF, 915.5 KB)
Contract awarded and work set to start - July 2024 notification (PDF, 406.23 KB)
Changed traffic conditions on the Kamilaroi Highway at Spring Creek from Monday 22 July - August 2023 notification (PDF, 80.49 KB)
Changed traffic conditions on Kamilaroi Highway at Spring Creek
Reports
Media releases
- 12 September 2024
Work to start on Monday on the new Spring Creek Bridge - 17 July 2024
On your marks: tools at the ready to build the new Spring Creek Bridge - 18 January 2023
Call for tenders to build the new Spring Creek Bridge near Narrabri - 9 August 2023
Work starts to build a side track for Spring Creek Bridge replacement.
Personal Information Collection Notice: Transport for NSW is committed to protecting your privacy and ensuring your personal and health information is managed according to law. Find out why we collect your personal information and how we use and manage it by reading our privacy statement or phone 13 22 13 to request a copy.