Mariyung Fleet - upgrading existing maintenance and stabling facilities
Project overview
Modifications are needed to existing maintenance and stabling facilities at Eveleigh, Gosford, Broadmeadow, Lithgow, Hamilton, Wollongong and Port Kembla to accommodate the Mariyung Fleet.
Image

Image controls:
Project overview
Modifications to the Eveleigh, Gosford, Broadmeadow / Hamilton, Lithgow, Wollongong and Port Kembla facilities are now complete.
Eveleigh facility
Modifications have been completed within the existing maintenance and stabling facilities at Eveleigh to accommodate the new trains. Changes include:
- Track and siding extensions
- Supporting infrastructure including extension of overhead wiring, signals, walkways, fencing and lighting to support the above
- Testing and stabling the new fleet
- Maintenance such as minor repairs and cleaning.
Project news
Planning documents
- New Intercity Fleet Eveleigh Facility Determination Report (PDF, 4.23 MB)
- New Intercity Fleet Eveleigh Facility Review of Environmental Factors (PDF, 5.99 MB)
- New Intercity Fleet Eveleigh Facility Review of Environmental Factors Appendix A Noise and Vibration Assessment (PDF, 2.74 MB)
- New Intercity Fleet Eveleigh Facility Review of Environmental Factors Appendix B Statement of Heritage Impact (PDF, 19.55 MB)
- New Intercity Fleet Eveleigh Facility Review of Environmental Factors Appendix C Visual Impact Assessment (PDF, 7.45 MB)
Gosford Stabling Yard
Modifications have been completed within the existing facility at Gosford to accommodate the new trains. These changes included:
- Upgrading concrete walkways including new hand railings
- Installing lighting
- An extension to existing decanting facilities and relocation of train car markers.
Project news
Wollongong facility
Modifications have been completed within the existing facility at Wollongong to accommodate the new trains. These changes included:
- Installing new steel elevated walkway for rail staff
- Extending the existing staff concrete walkways
- Installing lighting and CCTV
- Relocating track crossings, signal and power service and train car markers.
Port Kembla facility
Modifications have been completed within the existing facility at Port Kembla to accommodate the new trains. These changes included:
- Extending the existing staff concrete walkways including new hand railings.
- Installing lighting
- Relocating under track crossings, signal and power service and train car markers.
Lithgow facility
Modifications have been completed within the existing facility at Lithgow to accommodate the new trains. These changes included:
- Updated signage
- Line marking the existing staff concrete walkways
- Installation of train car markers.
Hamilton facility
Modifications have been completed within the existing facility at Hamilton to accommodate the new trains. These changes included:
- Extension to existing decanting facilities
- Buffer stops modification work
Broadmeadow facility
Modifications have been completed within the existing facility at Broadmeadow to accommodate the new trains. These changes included:
- Extending the existing staff concrete walkways
- Extension to existing decanting facilities and relocation of train car markers.
Project News
Please contact us if you could like to join the project mailing list.
Email projects@transport.nsw.gov.au
Call 1800 684 490
For urgent enquires or complaints regarding construction activities, please call 24 hours 1800 775 465