New Richmond Bridge - Stage 1
Project overview
The Australian and NSW governments have committed $515 million to deliver the New Richmond Bridge project. In Stage 1, Transport for NSW will upgrade two key roundabouts on The Driftway, at Blacktown and Londonderry roads, to improve safety and traffic flow and increase flood resilience.

Latest news
July 2025 – Project Notification – Site compound set up and investigation work starts
From Monday 28 July, early investigation work starts, and the site compound will be set up. You can read more in our July project notification (PDF, 505.16 KB).
June 2025 – Contract award and start of work
Transport for NSW has awarded a major construction contract to BMD Constructions to deliver Stage 1 of the New Richmond Bridge project. Stage 1 will deliver safety and flood resilience benefits on The Driftway by upgrading the intersections at Blacktown Road and Londonderry Road.
Work will begin from July 2025 to prepare and set up the site compound and other areas. Stage 1 construction is expected to be complete in 2027.
Project information
Stage 1 construction will focus on improving safety and flood resilience at the two key intersections on The Driftway including:
- new roundabout at Londonderry Road: The upgrade will improve the intersection to a new roundabout that will also include an extra southbound lane. The improved intersection with extra southbound capacity will improve the Londonderry Road flood evacuation route to help traffic flow during flooding events
- new roundabout at Blacktown Road: At the Blacktown Road end, the roundabout will improve safety at the intersection and a new bridge across Rickabys Creek will improve flood resilience.
Shoulder widening on The Driftway would be completed as part of Stage 2B of the New Richmond Bridge project, when further funding is available.
For more information on the New Richmond Bridge project, see the December 2024 community update (PDF, 7.32 MB).
Background
Transport for NSW has been developing the New Richmond Bridge project. This significant and much-needed project will reduce traffic congestion between Richmond and North Richmond and improve evacuation options and connectivity during significant flooding events.
Stage 1 early work was completed in 2024. This work included building and relocating additional Sydney Water mains at various locations along The Driftway between Blacktown Road and Londonderry Road.
The proposed project received environmental approval in March 2022. For further information please see the Review of Environmental Factors and Submissions Report located in Project Documents below.
For more information on the New Richmond Bridge project, see the December 2024 Community Update.
Next steps
Work will begin from July 2025 to prepare and set up the site compound and other areas. Stage 1 construction is expected to be complete in 2027.
Community information
Frequently asked questions (FAQs)
Project documents
Some documents on this page may not comply with accessibility requirements (WCAG).
If you are having trouble accessing information in these documents, please contact us.
Community updates
- December 2024 community update (PDF, 7.32 MB)
- November 2021 community update
New Richmond Bridge and traffic improvements - The Driftway (Stage 1) Review of Environmental Factors on display.
Project notifications
- July 2025 project notification (PDF, 505.16 KB)
Site compound set up and investigation work starts - January 2024 project notification (PDF, 1.2 MB)
Continuing early work for The Driftway upgrade until Friday 1 March 2024 - December 2023 project notification (PDF, 296.38 KB)
Night work on The Driftway - Tues 12 and Wed 13 December 2023. - October 2023 project notifiation (PDF, 315.43 KB)
Continuing early work for The Driftway upgrade until Wednesday 31 January 2024. - September 2023 project notification (PDF, 242.31 KB)
Tree removal for The Driftway upgrade from 20 September 2023. - June 2023 project notification (PDF, 366.1 KB)
From Monday 10 July 2023, Transport for NSW will start the investigation work in the road corridor. The Sydney Water main relocation early work will recommence from Monday 31 July 2023 and is expected to be complete by late October 2023. - April 2023 project notification (PDF, 621.74 KB)
Stage 1 The Driftway early work from Wednesday, 26 April 2023. New Richmond Bridge and traffic improvements - Stage 1 The Driftway
Community Update April 2022.
September 2021 project notification
Day investigation work on The Driftway, Londonderry from 6 September.
- November 2020 project notification
Richmond Bridge and traffic improvements project, investigations on The Driftway, Richmond.
REF documents
- New Richmond Bridge and traffic improvements – Stage 1 The Driftway October 2024 Addendum Review of Environmental Factors – Main Report and Appendix A-B-C-D (PDF, 3.35 MB)
- New Richmond Bridge and traffic improvements – Stage 1 The Driftway October 2024 Appendix E Addendum Biodiversity assessment report (PDF, 14.95 MB)
- New Richmond Bridge and traffic improvements – Stage 1 The Driftway October 2024 Appendix F Operation Traffic noise assessment report (PDF, 8.32 MB)
- New Richmond Bridge and traffic improvements – Stage 1 The Driftway October 2024 Appendix G Aboriginal Heritage stage 1 PACHCI Assessment (PDF, 7.96 MB)
- New Richmond Bridge and traffic improvements - Stage 1 The Driftway October 2024 Appendix REF - Appendix H Part 1 (PDF, 42.11 MB)
- Appendix H Part 2 (PDF, 18.95 MB)
- Appendix H Part 3 (PDF, 16.59 MB)
- Appendix H Part 4 (PDF, 14.89 MB)
- Appendix H Part 5 (PDF, 10.11 MB)
- Appendix H Part 6 (PDF, 7.11 MB)
- Appendix H Part 7 (PDF, 21.97 MB)
- Appendix H Part 8 (PDF, 14.31 MB)
- Appendix H Part 9a (PDF, 67.03 MB)
- Appendix H Part 9b (PDF, 19.06 MB)
- Appendix H Part 9c (PDF, 9.67 MB)
- Rickeby's Creek (PDF, 16.47 MB)
New Richmond Bridge and traffic improvements – Stage 1 The Driftway Submissions Report
April 2022.
- New Richmond Bridge and traffic improvements – Stage 1 The Driftway Submissions Report
Appendix A – Concept Design Plans. - New Richmond Bridge and traffic improvements – Stage 1 The Driftway Submissions Report
Appendix B – Contamination Waste Classification Assessment. - Review of Environmental Factors Main Report and Appendices A & B
New Richmond Bridge and traffic improvements - Stage 1 - The Driftway (Main Report and Appendix A & B). - REF - Appendix C
Biodiversity assessment report. - REF - Appendix D
Flooding and drainage investigation. - REF - Appendix E
Noise and vibration assessment. - REF - Appendix F
Landscape character and visual impact assessment report. - New Richmond Bridge and traffic improvements - Stage 1 The Driftway concept design plans
Contact us
For further information about this project, please contact:
Phone: 1800 240 066
Email: thedriftway@transport.nsw.gov.au