Newell Highway Upgrade - New Dubbo Bridge project

Reviewed

Project overview

Together, the Australian and New South Wales Governments are investing $220.2 million in the New Dubbo Bridge project to improve traffic congestion in Dubbo and enhance access across the Macquarie River during flood events.

Latest news

Mar 2023 - Start of Major Work for New Dubbo Bridge

Major work is underway on the New Dubbo Bridge project. We will keep the community updated with any construction updates and impacts. For more informaion, read the full media release here.

Jan 2023 - Closure of Brisbane Street from 9 January 2023

Work is currently underway on the new Brisbane and Darling Street intersection as part of the New Dubbo Bridge project.

As part of these works, Brisbane Street between Myall Street and River Streer will be closed from Monday 9 January for 2 months with a detour in place.

Find out more by reading the project notification letter.

Dec 2022 - Start of preparation for New Dubbo Bridge main works

In preparation for main works on the New Dubbo Bridge project, Abergeldie Complex Infrastructure will begin site establishment and investigation works. Work will take place in various locations across the project site, starting in December 2022 and continuing into the start of 2023.

No work will take place over Christmas, New Year, or the Australia Day public holiday. For more information, including a map of the site locations, read the project notification.

Project information

Background

The New Dubbo Bridge provides a second high level river crossing in Dubbo during flood events and will maintain reliability for local, commuter and heavy freight traffic through Dubbo during these events.

Following investigation of six strategic options and community consultation, River Street was announced as the preferred route for the new bridge in May 2017.

The preferred option has been chosen to improve freight efficiency on the Newell Highway, reduce traffic congestion and provide an additional route during flood events. It will assist in easing congestion in Dubbo when needed most.

Features

The 660 metre bridge will connect the western side of the Macquarie River to River Street, travelling over the flood plain west of the river. The Newell Highway Upgrade - New Dubbo Bridge project will also include:

  • New and upgraded intersections at Whylandra Street, and the Newell Highway
  • Realigning the Newell Highway with new separated lanes north of Whylandra Street
  • Upgrading the intersection at Bourke Street and River Street.

What is happening now?

Full funding for the Newell Highway Upgrade - New Dubbo Bridge project has been confirmed, comprising of $176 million from the Australian Government and $44 million from the NSW Government.

The detailed design for the New Dubbo Bridge has now been completed.

During the detailed design process, Transport for NSW worked with stakeholders and carried out survey, geotechnical and utility investigation works.

Workshops have been regularly held to refine the design and plan for construction so that we minimise impacts to traffic wherever possible.

Transport for NSW will continue to consult with the community during each phase of the project.

The project will provide significant employment opportunities as well as local and regional benefits to the Central West when major work is set to start to commence in 2023.

What happens next?

The early works supporting the main road and bridge construction are scheduled to start this year with the first early works tender being issued on 17 March 2022 for the

Brisbane St and Darling St intersection. Tenders for this early works package will close on Tuesday 19 April 2022.

An upgrade of the Mitchell Highway and Thompson Street intersection and test bridge piling in the flood plain will also commence this year.

In April 2022, Transport will call tenders for the main construction works and utility relocation works. The successful head contractor for the main construction contract is expected to be announced by the end of 2022 with work set to start at the beginning of 2023.

Local Contractors will also get the opportunity to attend an industry forum in Dubbo in May to network with pre-qualified tenderers. Businesses and suppliers can also register their interest to be involved in the project with the Industry Capability Network Gateway.

We will continue to update the community and key stakeholders in the lead up to and during construction.

Review of Environmental Factors

The Review of Environmental Factors (REF) assesses the potential social and environmental impacts of the project and identifies ways to minimise these impacts. View or download a copy of of the REF main report. The full report is on the project documents page.

 

Project map

View or download the project map.

 

New Dubbo Bridge - Artist impression

Artist impression

Community information

Frequently asked questions (FAQs)

Displays and posters

Maps

Plans

 

Project documents

Some documents on this page may not comply with accessibility requirements (WCAG).

If you are having trouble accessing information in these documents, please contact us.

 

Community updates

Reports

Media releases

  • 1 August 2022

    The first phase of the New Dubbo Bridge project is now underway.

  • 14 July 2022

    Contract awarded to build intersection as part of the New Dubbo Bridge project.

  • 12 July 2021

    Investigation works underway on new Dubbo Bridge.

Submissions reports

Consultation reports

Addendum Review of Environmental Factors

Preferred option report

Contact us

For further information about this project, please contact:

Phone: 1800 803 818

Email:dubboprojects@transport.nsw.gov.au