Spring Farm Parkway, Menangle

Reviewed

Project overview

Stage 1 of Spring Farm Parkway will provide a new four lane divided road extending about one kilometre connecting Menangle Road to Menangle Park Urban Release Area including an interchange over the Hume Motorway with City facing on and off ramps.

Latest news

October 2023 – Construction Update

Work is continuing to advance on Spring Farm Parkway Stage 1. The main drainage and service relocation works on Menangle Road have been completed. 

The construction of the bridge over the Hume Motorway is progressing with the completion of the bridge piers and retaining walls to facilitate the installation and placement of the bridge girders.

On the western side, we have constructed an acceleration lane for the trucks to exit directly onto the Hume Motorway. 

View the October – December 2023 construction update (PDF, 1.67 MB) for more information about what is coming up and how it may impact you.

Jul 2023 – Construction Update

Since our last update, we have completed the main drainage works on Menangle Road. We are halfway through the installation of the box culverts within the project boundary.

Construction of the new central bridge columns on the Hume Motorway median are continuing and the retaining wall panels for the bridge are being prepared.

From September 2023, traffic travelling on Menangle Road will be moved onto an alternate section of the road. These important alignment changes will allow further construction activities on Menangle Road. 

View the July - September 2023 construction update (PDF, 434.07 KB) for more information about what is coming up and how it may impact you.

Apr 2023 – Continuing work and traffic changes

Weekend and night work will continue from Tuesday 4 April to Friday 30 June 2023, to enable work on the Hume Motorway and Menangle Road and to reduce impact on road users. 

We will be working between 6pm Tuesdays to 5am Sundays with no more than five consecutive nights of work at a time, excluding public holidays and weather permitting. 

View the April 2023 notification (PDF, 424.9 KB)  for more information about this work.

If you have any questions or would like further information, please contact the project team on 1800 966 040 or springfarmparkway.community@georgiou.com.au

Jan 2023 - Continuing work

Weekend and night work will continue from Tuesday 10 January to Friday 31 March 2023, to enable work on the Hume Motorway and Menangle Road and to reduce impact on road users.

We will be working between 6pm Tuesdays to 5am Sundays, excluding public holidays, weather permitting. 

View the January 2023 notification (PDF, 1.16 MB) for more information about this work.

If you have any questions or would like further information, please contact the project team on 1800 966 040 or springfarmparkway.community@georgiou.com.au.

Oct 2022 – Continuing work and traffic changes

Weekend and night work will continue from Sunday 16 October to Friday 23 December, to enable work on the Hume Motorway and to reduce impact on road users. We will be working between 6pm and 5am Sunday to Thursday, weather permitting.

View the October 2022 notification (PDF, 1.5Mb) for more information about this work.

If you have any questions or would like further information, please contact the project team on 1800 966 040 or springfarmparkway.community@georgiou.com.au

Jun 2022 – Start of construction

Weekend and night work will commence in July from Monday 18 July to Friday 14 October, to enable works along the Hume Motorway. We will be working between 6pm to 7am, Sunday to Thursday.

Work will include widening the median strip on Hume Motorway, protection work around the support columns of the Mark Evans Bridge and construction of temporary access off the Hume Motorway.

If you have any questions or would like further information, please contact the project team on 1800 966 040 or springfarmparkway.community@georgiou.com.au

View the July 2022 night work notification (PDF, 311Kb) for more information.

Project information

Background

Transport for NSW appointed Georgiou Group Pty Ltd to deliver the Spring Farm Parkway Stage 1 earlier this year. Work has now commenced with major construction in July 2022.

Georgiou will continue to notify landowners of any potential impacts during construction.

To keep up to date with the latest works, check the project notifications. For the latest traffic updates, visit the Live Traffic website or check the Live Traffic NSW App.

Benefits

  • Connecting communities and cater for residential growth.
  • Providing a key east-west connection for residents of Macarthur.
  • Providing safe and efficient access to and from the Hume Motorway.
  • Improving travel time reliability and efficiency for road users.
  • Providing a safe and effective crossing for pedestrians and cyclists over the Hume Motorway to Broughton Anglican College.

Features

Stage 1 of Spring Farm Parkway includes:

  • new four lane divided road extending about 1km from Menangle Road, west over the Hume Motorway to Menangle Park Urban Release Area
  • upgrade 600m of Menangle Road at Menangle Park including a new signalised intersection at the Spring Farm Parkway
  • north facing exit ramp from the Hume Motorway onto Spring Farm Parkway and Menangle Road
  • north facing entry ramp from Spring Farm Parkway and Menangle Road to the Hume Motorway
  • a shared-use path on the southern side of Spring Farm Parkway to provide access to Broughton Anglican College
  • Four new signalised intersections including:
    • Spring Farm Parkway and Menangle Road
    • north facing exit ramp from the Hume Motorway onto Spring Farm Parkway and Menangle Road
    • north facing entry ramp from Spring Farm Parkway and Menangle Road to the Hume Motorway
    • access to the Menangle Park land release.

Download the Spring Farm Parkway Stage 1 project map (PDF, 4.55 MB).

Project timeline

Work commenced in July 2022 and is expected to be completed by late 2024.

Project documents

Some documents on this page may not comply with accessibility requirements (WCAG).

If you are having trouble accessing information in these documents, please contact us.

 

Community information

Frequently asked questions

  • FAQs
    Spring Farm Parkway Stage 1.

Community updates

Media releases

  • 28 June 2022 - Construction begins on Spring Farm Parkway
  • 26 November 2019 - Spring Farm Parkway submissions report now online

Contact us

For further information about this project, please contact:

Phone: 1800 966 040

Email: springfarmparkway.community@georgiou.com.au

or Transport for NSW

Email: springfarmparkway@transport.nsw.gov.au

Phone: 1800 366 816

Mail: PO Box 973 Parramatta NSW 2150