Singleton Bypass - New England Highway

Reviewed

Project overview

The Australian and New South Wales Governments have invested a total of $700 million to build the Singleton Bypass.

The eight-kilometre project will bypass five sets of traffic lights in the CBD and is the largest road infrastructure investment in Singleton's history.

Transport for NSW Singleton Bypass McDougalls Hill.

Interactive portal

To learn more about this project, view our interactive portal for more information.

Latest news

August-September 2025 – Out of hours work

ACCIONA will be carrying out work on the Singleton Bypass project alignment. To minimise traffic impact, work will be carried out at night between 6pm and 7am on weeknights, and on some weekends. Night work will continue from early August to the end of September 2025, weather permitting.

Work will take place along the New England Highway between Range Road at Whittingham and Rixs Creek Lane at Rixs Creek. Activities will include earthworks, utility relocation, road asphalting, line marking, placement of barriers and concrete, and delivery of bridge girders using cranes.

For more information, please see our latest community notification (PDF, 492.13 KB).

July work update - bridge girder installation near Orchard Lane

As part of construction activities for the Singleton Bypass, bridge girders will be installed over the Great Northern Railway near Orchard Lane from Tuesday 22 July to Friday 25 July 2025.

To take advantage of the Australian Rail Track Corporation (ARTC) possession period, work may need to occur during evening and night-time hours between 6pm and 7am across this four-day period, subject to weather conditions.

Work will take place near Orchard Lane, around two kilometres south of Singleton CBD, within the project corridor.

The new bridge forms part of the Singleton Bypass and will cross the Great Northern Railway at this location. Six girders, each 38 metres long and weighing 83 tonnes, will be installed using a 600-tonne crane.

This work has been assessed as having moderate noise impact. Equipment to be used includes lighting towers, generators, a crane, hand held tools and other machinery.

There will be no traffic disruptions, and vehicle access for local residents will be maintained at all times. Residents may notice workers, vehicles and activity from work compounds located at the New England Highway (Whittingham) and Army Camp Road (Glenridding).

Standard work hours are between 7am to 6pm, Monday to Friday, and 7am to 1pm, Saturday. Due to the timing of this activity, work may extend outside these hours.

For more information, please see our July 2025 community notification (PDF, 216.87 KB).

June work update – traffic changes on Putty Road, Glenridding

As part of construction activities for the Singleton Bypass, night work will be carried out on Putty Road near Carrington Street to install bridge girders over the road.

To minimise traffic impact, work will take place between 7pm and 5am on Monday 2 June 2025 and Tuesday 3 June 2025, weather permitting.

Work will be carried out on Putty Road near Carrington Street, Glenridding, about one kilometre south of Singleton CBD and 450 metres south of the Great Northern Railway line.

The new bridge forms part of the Singleton Bypass and crosses Putty Road at this location. Seven girders, each 33 metres long and weighing 83 tonnes, will be installed as part of this activity.

Traffic will be stopped in both directions for up to 20 minutes at a time between 7pm and 4am. Delays are expected and motorists are advised to follow the direction of traffic controllers and signage.

Pedestrians and cyclists will also be stopped briefly by traffic control during girder lifts.

Variable Message Signs (VMS) will be in place along Putty Road, John Street and surrounding side roads to advise motorists of the changed traffic conditions. Live updates will be available on LiveTraffic NSW.com.

This work has been assessed as having moderate noise impacts, with equipment such as lighting towers, generators, a 600-tonne crawler crane, light vehicles and traffic control to be used during the activity.

For more information, please see our June 2025 community notification (PDF, 157.62 KB).

May work update – traffic changes at Gowrie Gates

As part of construction activities for the Singleton Bypass, night work will be carried out near Gowrie Gates to install bridge girders over the New England Highway.

To minimise traffic impact, work will take place between 7pm and 4am on Tuesday 6 May 2025, weather permitting. Contingency nights are Wednesday 7 and Thursday 8 May 2025 if work cannot be completed as planned.

Work will be carried out near the intersection of New England Highway and Maison Dieu Road, about two kilometres north of Singleton CBD.

The new bridge is located 60 metres west of the existing rail bridge at Gowrie Gates and forms part of the new bypass. Five girders, each 33 metres long and weighing 83 tonnes, will be installed as part of this activity.

Traffic will be stopped in both directions for up to 20 minutes at a time between 9pm and 4am. Delays are expected and motorists are advised to follow the direction of traffic controllers and signage.

Local traffic on Maison Dieu Road will be detoured via Magpie Street. Pedestrians and cyclists may continue using the shared path but will be stopped briefly during girder lifts.

This activity will involve moderate noise levels with equipment such as lighting towers, generators, a 600-tonne crawler crane, and traffic control vehicles.

For more information, please see our latest community notification (PDF, 174.8 KB).

April-June 2025 - Out of hours work

ACCIONA will be carrying out work in the project corridor. To minimise traffic impact, work is being carried out at night between 6pm and 7am on weeknights. Night work will be carried out until end of June, weather permitting. 

Work will be carried out along the New England Highway from 300 metres north of Range Road at Whittingham to 1.8 kilometres north of Rixs Creek Lane at Rixs Creek. Works will also be carried out from Putty Road to New England Highway, including Carrington Street, Army Camp Road, Victoria Street and Orchard Lane.

For more information, please see our latest community notification (PDF, 504.81 KB).

February 2025 - Project update

Construction on the $700 million Singleton Bypass is progressing well, with girders now being placed on the 1.6-kilometre bridge across the Doughboy Hollow floodplain.

Read the February project update (PDF, 1.76 MB).

February 2025 - Out of hours work

ACCIONA will conduct out work in the project corridor. To minimise traffic impact, work will be carried out at night between 6pm and 7am on weeknights. Night work will be carried out from the start of February to the end of the March 2025, weather permitting. 

Work is being carried out along the New England Highway from 300 metres north of Range Road at Whittingham to 1.8 kilometres north of Rixs Creek Lane at Rixs Creek. Works will also be carried out from Putty Road to New England Highway, including Carrington Street, Army Camp Road, Victoria Street and Orchard Lane (utility work is subject to Ausgrid availability).

Please view the January 2025 project update (PDF, 365.87 KB).

December 2024 – Christmas and New Year shutdown period

There will be no construction work during the Christmas and New Year period. The site office will be closed from Monday 23 December and reopen on Monday 6 January. 

November 2024 - Out of hours work

ACCIONA is currently carrying out work in the project corridor. To minimise traffic impact, work is being carried out at night between 7pm and 5am on weeknights. Night work will be carried out until end of January, weather permitting. 

Work is being carried out along the New England Highway from 300 metres north of Range Road at Whittingham to 1.8 kilometres north of Rixs Creek Lane at Rixs Creek.

Please view the November project update (PDF, 224.78 KB).
 

October 2024 – Out of hours work

ACCIONA is currently carrying out work in the project corridor. To minimise traffic impact, work is being carried out at night between 7pm and 5am on weeknights. Night work will be carried out until Friday 15 November, weather permitting. 

Work is being carried out along the New England Highway from 300 metres north of Range Road at Whittingham to 1.8 kilometres north of Rixs Creek Lane at Rixs Creek.

Please view the latest project update (PDF, 302.28 KB).

September 2024 - Major work underway

On Thursday 5 September, the Singleton Bypass project reached a significant milestone with the first sod turned, marking the start of major construction. 

Work on the project will be carried out between 7am and 6pm on Monday to Friday and between 8am and 1pm on Saturday

September 2024 – Final project design available

Ahead of major work starting, ACCIONA has finalised the design of the project. The design can be viewed on this map (PDF, 33.07 MB).

Following community and stakeholder feedback and further consultation with property owners as well as additional investigation and survey work, some changes have been made to the project, including:

  • simplifying the road layout at the southern connection
  • revising the location of the Putty Road roundabout and northbound and southbound entry and exit ramps
  • adjusting the northbound exit ramp and roundabout at Gowrie
  • building a large detention basin at the Gowrie connection to manage stormwater run-off
  • adjusting the size of the southbound entry and exit loop ramp at the northern connection, to improve road safety when travelling from Rixs Creek Lane.
July 2024 - Site preparation

ACCIONA has started site preparation work along the project corridor, ahead of main construction work starting later this year.

Early work activities are continuing on the project, which are required to inform the detailed design and finalise the construction schedule. 

Our standard work hours are Monday to Friday between 7am and 6pm and Saturdays between 8am and 1pm. 

Please view the latest project update (PDF, 280.62 KB).

March 2024 – Contractor’s early work

ACCIONA has started its early work activities on the Singleton Bypass. Early work activities include additional site survey, geotechnical and utility investigations, and installing temporary exclusion fencing and erosion and sediment controls. These activities are required to inform the detailed design for the project.

Early work will be carried out along the New England Highway between Haggartys Lane and White Falls Lane to the south of Singleton and Maison Dieu Road and Rixs Creek Lane to the north of Singleton.

Work will also be carried out along the proposed project alignment to the west of the New England Highway and Singleton.

Work will be carried out from Monday 11 March to June 2024, weather permitting. We will be working Monday to Friday between 7am and 6pm and on Saturday between 8am and 1pm.

Please view the latest project update (PDF, 601.4 KB)

February 2024 – Singleton Bypass batting for microbats

A colony of microbats near the Singleton Bypass site won’t have to find a new ‘fur-ever’ home following the implementation of protective measures as part of the project’s Microbat Management Plan.

The purpose of the Microbat Management Plan is to avoid indirect impacts on the species. By implementing measures like not disturbing the culverts that provide homes for the microbats, these creatures won’t need to relocate during construction.

The preservation of threatened species, such as these microbats, is an important part of any Transport for NSW project.

Access the 27 February media release.

Pre-clearance Survey - Ecologist inspecting culvert for presence of microbats
November 2023 – Award of major contract

We are pleased to announce that Acciona Construction Australia Pty Ltd has been awarded a design and construction contract to deliver the Singleton Bypass.

Acciona will progress site investigations and finalise the detailed design in preparation for the start of major work in mid-2024. The project is expected to open to traffic in late 2026, weather permitting.

We will keep the community informed as the project progresses. 

Learn more about Acciona.

May 2023 - Early work

Transport for NSW started early work on the project in late 2022.

Early work activities include:

  • installing fencing along the corridor
  • demolition of existing buildings
  • relocation of power and communication public utilities
  • additional geotechnical investigations
  • additional ground survey.

Early work is being carried out Monday to Friday between 7am and 6pm and on Saturday between 8am and 1pm.

Please view the latest project update (PDF, 593.77 KB)

Project information

Background

The New England Highway is part of the inland Sydney to Brisbane National Land Transport Network and the primary route connecting the Upper Hunter with Maitland and Newcastle.

The highway passes through the centre of Singleton and carries around 26,000 vehicles, including more than 3700 heavy vehicles, each day.

Traffic volumes are predicted to increase in the next 25 years. The planned bypass of Singleton would improve the movement of freight and journeys for current and future traffic demands.

A preferred option for the bypass was announced in 2016 and involves building a new section of highway west of Singleton across the floodplain, starting near Newington Lane and rejoining the New England Highway north of McDougalls Hill.

The project was approved in August 2020.

Community engagement

Transport for NSW invited feedback from the community about the Singleton Bypass concept design and REF from December 2019 until March 2020.

During this time, Transport received a total of 154 submissions relating to the New England highway bypass of Singleton. All submissions made during the display period have been addressed and responded to in a submissions report.

The New England Highway bypass of Singleton Submissions Report relates to the REF prepared for the bypass and summarises the issues raised as well as responses to each issue raised by the community, stakeholders and government agencies

We will continue working with the community and stakeholders during construction of the project to understand issues and minimise impacts.

Environmental assessment

The concept design and Review of Environmental Factors (REF) were on display for public comment from Wednesday 18 December 2019 to Sunday 1 March 2020.

During this time, Transport for NSW received a total of 154 submissions relating to the New England highway bypass of Singleton. All submissions made during the display period have been addressed and responded to in a submissions report (PDF, 20.29 MB).

The New England Highway bypass of Singleton Submissions Report relates to the REF prepared for the bypass and summarises the issues raised as well as responses to each issue raised by the community, stakeholders and government agencies.

Addendum REF (May 2023) (PDF, 2.4 MB)

Following further consultation with property owners and additional investigations into the project constructability, it was determined that minor existing property acquisition adjustments were required to facilitate construction of the project. In addition, consultation with applicable utility providers, identified that utility adjustment work were also required outside of the REF approval area to tie into existing utilities.

Addendum REF (October 2023) (PDF, 27.57 MB)

Following response to community and stakeholder feedback, Transport has modified the project by providing a full interchange at Putty Road, extended the bridge over the floodplain and reconfigured the design at the southern connection. The full interchange will improve access to Singleton’s town centre from the bypass.

The Addendum REFs describe the proposed modifications, assessing consistency and potential environmental impacts along with any additional mitigation measures that may be needed to reduce potential impacts of the proposed modification.

Addendum REF (August 2024) (PDF, 9.34 MB)

An Addendum Review of Environmental Factors (AREF August 2024) has been prepared to determine the potential environmental and social impact and proposed mitigation measures for the final design of the Singleton Bypass.

The AREF addresses how the work will be managed including the proposed methods used to minimise the impact on:

  • the local community through traffic, access, noise and vibration
  • flora and fauna
  • soil, water and air quality
  • socio-economic
  • flooding
  • Aboriginal heritage.

Employment

If you are interested in work opportunities, please visit our employment page.

Next steps

In late 2023, Transport for NSW awarded a design and construction contract to Acciona Construction Australia Pty Ltd to deliver the Singleton Bypass.

Major work on the bypass started in early September 2024. The project is expected to open to traffic in late 2026, weather permitting.

Project documents

Some documents on this page may not comply with accessibility requirements (WCAG).

If you are having trouble accessing information in these documents, please contact us.

 

Community information

Frequently Asked Questions

Community updates

Project updates

Review of environmental factors

Addendum REF (August 2024)

Addendum REF (October 2023)

Addendum REF (May 2023) 

Review of Evironmental Factors (December 2019)

Contractor EPL documents

Reports

Preferred option report

Community consultation report

Preliminary feasibility assessment report

Media releases

  • 5 September 2024
    Major work starts on Singleton Bypass
  • 27 February 2024
    Singleton Bypass Project batting for Microbats
  • 26 November 2023
    Major contract milestone for Singleton Bypass
  • 19 November 2022 (PDF, 583.07 KB)
    Game-changing bypass a step closer with shortlist released.
  • 16 April 2021
    Community feedback delivers better bypasses for Singleton and Muswellbrook.
  • 20 January 2021
    Momentum builds for Singleton bypass.
  • 24 November 2020
    Singleton Bypass locked in to bust bottleneck.
  • 10 August 2020
    Planning for Singleton Bypass moves ahead.

Contact us

For further information about the project, please contact:

Project information and 24-hr construction response line : 1800 991 254

Email: SBP-community@acciona.com