Jenolan Caves Road
Project overview
Following the extreme weather event in March 2021, there have been significant impacts to Jenolan Caves Road at Hampton, Two Mile and Five Mile. Transport for NSW is undertaking extensive investigation and rehabilitation work to return the road to full capacity.

Latest news
July 2025 – Community update
Read how projects are progressing on Jenolan Caves Road in the July Community Update (PDF, 570.36 KB).
February 2025 - Detour in place for road closures on Jenolan Caves Road near Hampton
View the February notification (PDF, 236.85 KB) for more information.
December 2024 - Jenolan Caves Road near Hampton reopened to two-way traffic
- View the 19 December 2024 media release.
- View the December notification (PDF, 212.53 KB) for more information.
November 2024 - Road closures on Jenolan Caves Road in December
View the November notification (PDF, 407.88 KB) for more information.
October 2024 - Road closures on Jenolan Caves Road near Hampton 11 -15 November
View the latest October notification (PDF, 434.14 KB) for more information.
July 2024 - Vital slope work the next step in restoring Jenolan Caves Road near Hampton
Read more in the media release.
Subscribe to stay up to date with the latest information about work being carried out on Jenolan Caves Road.
Project information
Hampton
The works at the Hampton slope were extensive and complex. Workers were required to abseil down the slope in order to complete the work, which involved replacing several culverts as well as the installation of more than 200 soil nails and shotcrete at two separate locations. Work at the Hampton slope was completed in July 2024, two months ahead of schedule.
Critical remediation work at Carlos Creek, near Hampton began in July 2024 following the completion of the Hampton downslope.
The works to repair Carlos Creek were complex due to the unstable ground under the road. To improve the ground stability the project included installing 30 grout injection columns and 220 soil nails.
Crews used four light-weight drill rigs, known as Marinis, during the work. The machines were lowered over the side of the slope which drastically reduced the number of road closures required to complete the work.
The work at Carlos Creek was completed in December 2024, three months ahead of schedule.
Jenolan Caves Road at Hampton is now open to two-way traffic for the first time in almost 4 years.
A final layer of asphalt through both project sites will be laid in early 2025.
Images of Hampton
Hampton slope remediation project
Hampton slope soil nailing
Soil nailing on the Carlos Creek project
Two Mile
Remediation work at Two Mile on Jenolan Caves Road commenced in August 2024.
Work will require the installation of up to four rows of soil nails, up to eight metres each in length, with more than 1200 nails expected to be installed at nine failure sites along the Two Mile. As well as using soil nails to repair the slope failures, we are improving drainage infrastructure to better handle surface run-off during rainfall.
This extensive remediation work will take about 18 months to complete and will restore access to the Jenolan Caves precinct to its previous condition.
Images from Two Mile
Two Mile Carpark failure prior to works commencing
Two Mile Carpark failure prior to works commencing
Two Mile Carpark failure remediation progressing
Five Mile
A contractor was appointed to undertake a works delivery package for repairs to the Five Mile in September 2023, however, a further extreme rain event in April 2024 caused significantly more damage and the road is continuing to deteriorate. Further development work has since ceased while the long-term viability of Five Mile is considered.
Images of Five Mile
Slope failures on the Five Mile map
View larger version of map here (PDF, 429.76 KB).
Five Mile main failure
Infographics and Diagrams
Impacts of flooding on Jenolan Caves Road
Image gallery












Jenolan Caves Road
Jenolan Caves Road, Five Mile July 2022
Jenolan Caves Road
Jenolan Caves Road, Five Mile July 2022
Jenolan Caves Road
Jenolan Caves Road, Five Mile July 2022
Jenolan Caves Road
Jenolan Caves Road, Five Mile July 2022
Jenolan Caves Road
Jenolan Caves Road, Five Mile July 2022
Jenolan Caves Road
Landslip at Two Mile, July 2022
Jenolan Caves Road
Landslip at Two Mile, July 2022
Jenolan Caves Road
Landslip at Two Mile, July 2022
Jenolan Caves Road
Landslip at Five Mile on Jenolan Caves Road
Jenolan Caves Road
Landslip at Five Mile on Jenolan Caves Road
Jenolan Caves Road
Jenolan Caves Two Mile
Jenolan Caves Road
Stabilising the upslope at Hampton on Jenolan Caves Road
Project documents
Some documents on this page may not comply with accessibility requirements (WCAG).
If you are having trouble accessing information in these documents, please contact us.
Traffic Alerts and Notifications
- July 2025 - Changed traffic conditions on Jenolan Caves Road from Monday 7 July 2025 (PDF, 246.77 KB)
- February 2025 - Detour in place for road closures on Jenolan Caves Road near Hampton (PDF, 236.85 KB)
- December 2024 - Jenolan Caves Road near Hampton open to two-way traffic (PDF, 212.53 KB).
- November 2024 - Road closures on Jenolan Caves Road in December (PDF, 407.88 KB)
- October 2024 - Detour in place for road closures on Jenolan Caves Road near Hampton (PDF, 434.14 KB)
- August 2024 - Jenolan Caves Road at Hampton closures extended (PDF, 305.48 KB)
- August 2024 - Updated closures Jenolan Caves Road at Hampton (PDF, 308.22 KB)
- June 2024 - Updated closures Jenolan Caves Road at Hampton (PDF, 835.06 KB)
- May 2024 - Road closure on Jenolan Caves Road at Hampton (PDF, 326.06 KB)
- April 2024 - Road closure on Jenolan Caves Road at Hampton (PDF, 323.37 KB)
- January 2024 - Road closure on Jenolan Caves Road at Hampton (PDF, 306.41 KB)
- December 2023 - Repair work continues along Jenolan Caves Road (PDF, 271.04 KB)
- November 2023 - Jenolan Caves Road closure at Hampton from 7 November to 9 November (PDF, 214.56 KB)
- November 2023 - Shared zone for motorist and pedestrian safety around Jenolan Caves tourist precinct
- October 2023 - Jenolan Caves Road closure at Hampton from 7 November to 9 November (PDF, 214.56 KB)
- October 2023 - Repair work on Jenolan Caves Road from 9 October (PDF, 257.56 KB)
- July 2023 - Temporary closure of Jenolan Caves Road and Jenolan Caves House from Tuesday 18 July (PDF, 83.61 KB)
- March 2023 - Temporary nighttime road closure and detour of Jenolan Caves Road at Hampton from Monday 27 March (PDF, 304.45 KB)
- January 2023 - Two Mile now open
- October 2022 - Jenolan Caves Road closed
- April 2022 - No ticket, no entry: Limited access to Jenolan Caves Road over Easter long weekend
- April 2022 - Jenolan Caves Road to close ahead of forecast rain event
- March 2022 - Heavy patching along Jenolan Caves Road for emergency repair work
Community updates
- July 2025 community update - Jenolan Caves Road repairs (PDF, 570.36 KB)
- August 2024 community update - Jenolan Caves Road repairs (PDF, 852.74 KB)
- December 2023 - Frequently Asked Questions - Jenolan Caves Road – Hampton slope repair (PDF, 383.57 KB)
- December 2023 community update - Jenolan Caves Road – Hampton slope repair (PDF, 1.73 MB)
- December 2022 community update - Jenolan Caves Road
- May 2022 community update - Jenolan Caves Road
- November 2021 community update - Jenolan Caves Road
- September 2021 community update - Jenolan Caves Road
- May 2021 community update - Jenolan Caves Road
- April 2021 community update - Jenolan Caves Road
- April 2021 community update - Road closures
- March 2021 community update - Jenolan Caves Road
REF Documents
- Two Mile Hill slope restoration works in Jenolan Karst Conservation Reserve NPWS Decision Statement November 2024 (PDF, 258.45 KB)
- Review of Environmental Factors Two Mile Hill Slope Restoration November 2024 (PDF, 36.91 MB)
- Review of Environmental Factors Two Mile Hill Slope Restoration March 2022 (PDF, 21.12 MB)
- Jenolan Caves Road Five Mile Failure - Review of Environmental Factors for National Parks (PDF, 9.33 MB)
Media releases
- 19 December 2024
Jenolan Caves Road reopens to two-way traffic near Hampton after almost four years - 22 July 2024
- Vital slope work the next step in restoring Jenolan Caves Road near Hampton
- 12 July 2024
Two Mile the next step in Jenolan Caves Road restoration - 21 December 2023
Abseiling workers to lead repairs on Jenolan Caves Road near Hampton - 9 November 2023
Shared zone for motorist and pedestrian safety around Jenolan Caves tourist precinct. - 21 September 2023
Key milestone reached to reinstate all access points to Jenolan Caves Jenolan Caves Road to reopen following landslip.
- 24 November 2021
Work powering ahead to restore Jenolan Caves Road. - Remediation work progresses on Jenolan Caves Road
31 August 2021. - Jenolan Caves Road to reopen at Hampton
25 May 2021. - Two mile re-opening to boost local tourism
6 May 2021. - Road network restoration under way following floods
2 April 2021.
Contact us
For further information about this project, please contact:
Phone: 1800 167 499