Sydney Harbour Bridge Cycleway Ramp
Project overview
Explore detailed design below to learn more about the rich history of Sydney Harbour Bridge and how the new cycle ramp will improve the cycling experience for all at this iconic landmark.
Image
Image controls:
Image






Image controls:
Project information
Project status
Arenco (NSW) Pty Ltd has been appointed to build the Sydney Harbour Bridge Cycleway Ramp Project. Construction is progressing well. Subject to weather or any unforeseen circumstances, we anticipate the cycleway to open this summer. We’ll announce an opening date in the coming weeks and keep the community updated as work progresses.
The project includes:
- a new elevated linear bike ramp, with a three metre wide deck, removing the hazard of navigating the existing stairs, providing a safer north-south cycle link and improving accessibility for all bike riders.
- a new 2.5m wide two-way dedicated cycle path on Alfred Street South to improve safety by separating cyclists, motorists and pedestrians.
- new shared paths on Alfred Street South and Lavender Street, and upgrades to the Lavender Street crossing and roundabout to improve the cycling and walking experience.
- removal of up to 15 parking spots to facilitate footpath widening and relocation of the bus stop on Alfred Street South.
Benefits
The linear ramp and shared cycle path will:
- Provide a critical north-south link in the current cycling network
- Provide improved accessibility for bike riders of different levels of ability and mobility
- Remove the hazard of navigating the existing stairs at the Sydney Harbour Bridge
- Promote physical activity and healthy lifestyles and reduce the number of cars on the road
- Improve the safety of bike riders, pedestrians and motorists travelling around the northern end of Alfred Street South at the Lavender Street roundabout
- Improve safety by separating pedestrian and bike rider traffic around Milsons Point Station near Burton Street
- Provide a safer option than a spiral ramp due to potential congestion of pedestrians, bike riders and motor vehicles
- Support the predicted future growth in the number of bike riders travelling north and south of the Sydney Harbour Bridge
The existing Burton Street stairs have heritage significance as original fabric of the Sydney Harbour Bridge. The stairs will be open for use during construction and retained once the cycleway is complete.
What’s happening
November work activities
Day work
- Installing bronze balustrades, bump rails and pavers on the ramp.
- Modifying services on Alfred Street South and Lavender Street.
- Ongoing footpath and road work along Alfred Street South to build the new two-way cycle path and shared path.
- Installing new kerbs, gutters and footpaths and new cyclist on-ramp at the southern end of Middlemiss Street and Lavender Street.
- Laying pavers along Alfred Street South and in front of Milsons Point Station inside work areas.
- Landscaping in Bradfield Park.
Night work
- Ongoing footpath and road work along Alfred Street South to build the new two-way cycle path and shared path.
- Testing the watermain on Alfred Street South and Middlemiss Street.
- Trenching across Alfred Street South to place overhead powerlines underground. Alfred Street South, near Lavender Street, will be temporarily closed during this work. Access to residential buildings will be maintained via traffic control.
- Removing and replacing the footpath and kerb at the corner of Middlemiss Street and along Lavender Street. 
 • Building the new permanent in-lane bus stop on Alfred Street South.
This night work will be carried out from 6pm to 7am on the following nights:
- Wednesday 5 and Thursday 6 November
- Wednesday 12 and Thursday 13 November
- Wednesday 19 and Thursday 20 November
For more information see the November 2025 construction update (PDF, 333.75 KB).
 
Temporary cyclist access changes at Middlemiss Street
From Friday 10 October the dedicated bike lane exit at Middlemiss Street will be temporarily unavailable for around four weeks. Cyclists travelling northbound will need to detour via Arthur Street and Lavender Street. Cyclists travelling southbound can continue using Middlemiss Street. See map (PDF, 3.27 MB) for details of temporary changes.
Project documents
Some documents on this page may not comply with accessibility requirements (WCAG).
If you are having trouble accessing information in these documents, please contact us.
Community updates
- November 2025 weekend construction notification (PDF, 333.75 KB)
 Construction update
- October 2025 weekend construction notification (PDF, 526.8 KB)
 Updated construction update
- October 2025 construction notification (PDF, 474.2 KB)
 Construction update
- September 2025 construction notification (PDF, 738.75 KB)
 Construction update
- August 2025 construction notification (PDF, 473.81 KB)
 Construction update
- July 2025 construction notification (PDF, 785.19 KB)
 Construction update
- June 2025 construction notification (PDF, 514.01 KB)
 Construction update
- May 2025 construction notification (PDF, 920.61 KB)
 Construction update
- April 2025 construction notification (PDF, 736.76 KB)
 Construction update
- March 2025 night work notification (PDF, 230.13 KB)
 Night work notification 30 and 31 March
- March 2025 night work notification (PDF, 414.84 KB)
 Night work notification
- March 2025 construction notification (PDF, 453.85 KB)
 Construction update
- February 2025 construction notification (PDF, 523.38 KB)
 Construction update
- January 2025 community letter (PDF, 213.47 KB)
 Have your say - night work proposal
- December 2024 / January 2025 community notification (PDF, 875.51 KB)
 Construction update
- November 2024 community notification (PDF, 543.89 KB)
 Work is progressing in preparation for the start of main construction in Bradfield Park
- August 2024 community notification (PDF, 1.62 MB)
 Sydney Harbour Bridge Cycleway Northern Access Project
- May 2024 community notification (PDF, 700.34 KB)
 Site investigations night works
- May 2024 community notification (PDF, 514.09 KB)
 Project award and site investigations
- November 2023 community notification (PDF, 396.61 KB)
 Planned night work
- October 2023 community notification (PDF, 298.74 KB)
 Planned night work
- September - October 2023 community notification (PDF, 349.71 KB)
 Site investigations
- August 2023 community notification (PDF, 747.2 KB)
 Submissions Report.
- February 2023 community notification (PDF, 349.13 KB)
 Site investigations.
- November 2022 community notification - Kirribilli Markets relocation. 
- November 2022 community notification - Review of Environmental Factors. 
- November 2022 community notification - Site Investigations. 
- April 2022 Consultation Outcomes Report
- March 2022 Response to community questions
- March 2022 Response to Bradfield Park Central community proposal
- March 2022 Arcadis technical review
- August 2021 Community Consultation Report
- June 2021 FAQs
- June 2021 project overview
- June 2021 community update
Detailed design maps
Fact sheets and frequently asked questions (FAQs)
Submissions report
- Submissions Report (PDF, 11.77 MB)
- Appendix B Archaeological Research Design (PDF, 8.1 MB)
- Appendix C Updated SOHI (PDF, 14.1 MB)
- Appendix D Addendum LCVIA (PDF, 4.35 MB)
- Appendix E Traffic Impact Assessment (PDF, 13.3 MB)
- Appendix F Arboricultural Impact Assessment (PDF, 16.1 MB)
- Appendix G North Sydney Council mark-ups (PDF, 2.88 MB)
- Appendix H Section 171 (PDF, 225.43 KB)
Northern cycle ramp documents (current)
- Community User and Bike Group (CBUG). 
- Review of Environmental Factors (REF)
 Main report.
- Appendix A and B
- Appendix C
 Landscape character and visual impact assessment.
- Appendix D
 Statement of heritage impacts.
- Appendix E
 Biodiversity Searches and Test of Significance.
- Appendix E
 Protected Matters Search - MNES layers.
- Appendix F
 Noise and vibration impact assessment.
- Appendix G
 Traffic and transport impact assessment.
- Appendix H
 Preliminary Site Investigation.
- Appendix I
 Preliminary Arboricultural Report.
- Appendix J
 Aboriginal heritage due diligence assessment
- February 2022 Design Jury Report
- November 2021 ASPECT Studios design report
- November 2021 REALMstudios design report
- November 2021 Civille design report
- Sydney Harbour Bridge Cycleway Aboriginal Design Principles (PDF, 11.75 MB)
- Detailed Heritage Framework - Draft
Northern cycle ramp documents (superseded)
- November 2017 community update - Cycleway Access Proposals. 
- Sydney Harbour Bridge Northern Cycle Ramp. 
- Appendix A – Site Constraints. 
- Appendix B – Preliminary Strategic Options. 
- Appendix C – Case studies for outdoor elevators/escalators. 
- Appendix D – Cycle ramp options feasibility study – 2012. 
- March 1999 Feasibilty Study
Southern cycle ramp documents
- November 2017 review of environmental factors report - Sydney Harbour Bridge Southern Cycleway. 
- November 2017 review of environmental factors report - Appendix A - Urban design, landscape and visual impact assessment. 
- November 2017 review of environmental factors report - Appendix B - Consideration of clause 228(2) factors and matters of national environmental significance. 
- November 2017 review of environmental factors report - Appendix C - Statutory consultation checklists. 
- November 2017 review of environmental factors report - Appendix D - Non-Aboriginal heritage assessment. 
- November 2017 review of environmental factors report - Appendix E – Noise and vibration impact assessment. 
- November 2017 review of environmental factors report - Appendix F – Traffic and transport assessment. 
- November 2017 review of environmental factors report - Appendix G – Socio-economic impact assessment. 
- November 2017 review of environmental factors report - Appendix H - Biodiversity impact assessment. 
- November 2017 review of environmental factors report - Appendix I – Arboricultural impact assessment. 
- November 2017 review of environmental factors report - Appendix J - Preliminary site investigation. 
- November 2017 review of environmental factors report - Appendix K – AHIMS search result. 
- November 2017 review of environmental factors report - Appendix L - Preliminary options testing. 
Personal Information Collection Notice: Transport for NSW is committed to protecting your privacy and ensuring your personal and health information is managed according to law. Find out why we collect your personal information and how we use and manage it by reading our privacy statement or phone 13 22 13 to request a copy.
Contact us
For further information about this project, please contact:
Phone: 1800 581 595
Email:sydneyharbourbridgeprojects@transport.nsw.gov.au